The Department of Veterans Affairs is seeking sources to replace and maintain the Washington DC VA Medical Center’s 19-location parking gate system. - Government buyer: Department of Veterans Affairs, Veterans Health Administration, Network Contracting Office 5; Washington DC VA Medical Center. - OEMs and named vendors: Johnson Controls, Inc. (JCI) is a mandatory subcontractor for PIV readers and related PACS hardware. The system must integrate with the existing Software House C•CURE 9000 PACS and iSTAR-family controllers. - Equipment requested: 17 standard barrier-gate operators, one long-arm barrier operator, one slide-gate operator, one spare standard operator, 19 remote I/O monitoring and control devices, 19 IP event cameras, and 19 PIV/PIV-I readers with associated access-control hardware. Relocatable foundations and flexible wiring are also required at two parking lots; quantity is to be confirmed by site survey. - Services: Remove existing equipment; install, integrate, test, and commission the system; provide training, documentation, and a minimum one-year parts-and-labor warranty. Provide a service agreement for a base year plus four one-year options. - Notable requirements: Installation within 120 days after Notice to Proceed; gate operators must meet applicable UL 325 and ASTM F2200 safety requirements. Readers must be on the GSA FIPS 201 Approved Products List and use OSDP v2 secure-channel communications. Cameras must comply with Section 889 and include at least 256 GB of high-endurance local storage. Remote monitoring requires a FedRAMP-authorized or VA-approved platform, dedicated cellular/wireless communications, 24/7 alert monitoring, quarterly preventive maintenance, and at least 98% monthly availability per gate.

Description

SUMMARY The Department of Veterans Affairs (VA), Veterans Health Administration (VHA), Network Contracting Office (NCO) 5, is issuing this Sources Sought Notice to identify vendors that are interested in and capable of providing the required services. The Washington DC VA Medical Center requires a contractor to provide a Parking Gate System Replacement, Remote Monitoring, PIV Badge Reader Integration and 5 year Service Agreement for the facility. Interested vendors should review the Statement of Work (SOW) to determine the specific services required. NCO 5 is seeking responses from firms that are interested in this procurement and possess the resources, capabilities, and qualifications necessary to perform these services. Anticipated NAICS CODE: 561621 Security Systems Services (except Locksmiths)PSC CODE: J063 Please submit your capabilities statement and provide responses to all questions listed below.

SOURCES SOUGHT NOTICE: 36C24527Q0083 Business name (including Unique Entity ID (SAM.gov)) Business type, socio-economic status (e.g., Veteran-Owned, Woman-Owned, Disadvantaged Small Business, 8(a), etc.) Person of contact (including telephone number & email address). Capability statement and summary of previous experience providing these types of services for the Veterans Health Administration or other similar facilities. Available contract vehicles (GSA FSS, etc.) for use by Department of VA (including applicable NAICS) Brief Summary of categories of services that your company can/cannot provide. Certification(s) / Licenses for meeting the local requirements to provide these services at the DC VAMC (if applicable) Confirmation that your organization has the capability and expertise to meet the performance requirements while complying with applicable limitations in subcontracting by responding to the questions below with your response: Do you intend to self-perform this effort? If you are located outside the immediate area, how will you self-perform? Or do you intend to subcontract work under this contract? If you intend to subcontract work under this contract, how will you ensure compliance with the limitations on subcontracting?

Response Instructions: Respond to this Notice 36C24527Q0083 by 12-15-2026 @ 10 AM ET.Send all responses to Billie.Pratt@va.gov Subject line on email:36C24527Q0083 Sources Sought Notice | Company Name

STATEMENT OF WORK Parking Gate System Replacement, Remote Monitoring, PIV Badge Reader Integration and Service AgreementDepartment of Veterans Affairs | Washington DC VA Medical Center50 Irving Street NW, Washington, DC 20422Draft dated October 27, 2026

1. BACKGROUND The Washington DC VA Medical Center (VAMC) controls vehicle access to its parking areas, service drives and the separated Fisher House locations through nineteen (19) automated gates: eighteen (18) barrier-arm gates and one (1) slide gate at Utility Building 8. The existing gate operators are at end of service life, depend on in-ground loop detectors in deteriorated asphalt, and experience frequent vehicle strikes and extended downtime. The existing card readers at the gates are not uniformly capable of reading Personal Identity Verification (PIV) credentials, and VA Police Service cannot centrally manage parking-area access. VA requires (a) replacement of the gate operating equipment with commercial, high-duty equipment and above-ground vehicle detection, (b) remote status monitoring, event cameras and remote gate control for authorized VA personnel, (c) all-new PIV badge readers at each gate, furnished and installed by Johnson Controls, Inc. (JCI) as a subcontractor to the prime, and integrated into the VA Police Service physical access control system (PACS) so VA Police can control access to the facility parking areas, and (d) a firm-fixed-price service agreement covering a base year plus four (4) one-year option periods.

2. SCOPE OF WORK The Contractor shall furnish all management, supervision, labor, equipment, materials, tools, transportation, subscriptions, and subcontracted services (including the mandatory JCI subcontract in Section 5) necessary to remove the existing gate equipment and furnish, install, test, commission, warrant, monitor, and maintain a complete and operational parking gate and access control system at the 19 gate locations, in accordance with this SOW, manufacturer requirements, and the referenced codes and standards. Equipment brand names in this SOW, other than the JCI/PACS requirement in Section 5, are "or equal."

3. LOCATIONS AND EXISTING CONDITIONS ItemLocation / TypeQuantityNotes 1Barrier-arm gates (standard duty, 12 14 ft arm)17Parking lots and service drives; includes separated Fisher House locations. 2Barrier-arm gate (long arm, approx. 20 ft)1Heavy-duty operator; status reporting appropriate to hardware. 3Slide gate — Utility Building 81Reuse existing gate panel; convert from top track to bottom steel cantilever track. 4Lots 3B and 4BGates as installed (verify)Relocatable (forklift-movable) foundations and flexible wiring for planned two-way operation. Total gate locations19 Contractor shall verify all locations and conditions during the mandatory site visit. Existing 120 VAC power is available at each gate location. Any electrical deficiency found during the site survey shall be reported in writing to the COR before installation; correction of pre-existing deficiencies will be addressed by modification if outside this scope.

4. TECHNICAL REQUIREMENTS — GATE SYSTEM 4.1 Removal and Disposal Remove existing operators, arms, controls, and abandoned detectors at all 19 locations; legally dispose of all removed material off VA property (batteries recycled per EPA/DC regulations). Clean and prepare concrete pads. Removal and replacement shall be sequenced so that no parking area loses all vehicle access at once without a VA Police-approved traffic plan.

4.2 Barrier Gate Operators Commercial/industrial, high-cycle (continuous-duty) DC barrier operators listed to UL 325 and installed per ASTM F2200 where applicable. Integral or supplemental battery backup at every location. Behavior on loss of primary power (fail-open or fail-secure) shall be programmable per location and set as directed in writing by the Chief, VA Police Service. LED-illuminated arms (high-visibility), breakaway/swing-away arm flanges at standard-arm locations, and arm-displacement (arm-missing) contacts wired to the monitoring system. Above-ground radar ("virtual loop") vehicle detection configured for safety, arming, reset and free-exit functions as required per lane; no reliance on in-pavement loops at barrier locations. One (1) spare barrier operator, identical to the installed standard model, delivered to VA as Government property.

4.3 Slide Gate — Utility Building 8 Convert the existing gate panel from top (aluminum) track to bottom steel cantilever track with carriages, guide rollers and fabrication as required. Furnish and install a high-traffic commercial DC slide gate operator rated for the gate weight/length, with battery backup, monitored contact edges, wireless edge transmitter, and photo-eye entrapment protection meeting UL 325 Type B1/B2 requirements; reconnect to existing loop detectors where serviceable.

4.4 Relocatable Foundations — Lots 3B and 4B Provide relocatable, forklift-movable operator foundations and flexible wiring arrangements so the Contractor or VA can relocate operators for large deliveries or lot reconfiguration. Contractor shall confirm quantity during the site survey.

4.5 Remote Monitoring and Control Provide a remote I/O device at each of the 19 gates reporting operator fault, gate position, arm displacement, and communication-loss conditions, and relay outputs for remote open, hold-open, scheduled operation and release. The dashboard shall distinguish an operator fault from a communication loss, and an acknowledged relay command from confirmed gate position where feedback is available. All life-safety and entrapment-protection functions shall remain under local operator control; remote commands shall never override local safety devices. Communications shall use dedicated contractor-furnished cellular/wireless service used solely for the gate system. No component shall connect to the VA enterprise network except the JCI PACS equipment addressed in Section 5, and only as approved by VA OIT/ISSO.

4.6 Event Cameras Nineteen (19) IP cameras with alarm I/O, one per gate, compliant with Section 889 of the FY2019 NDAA (FAR 52.204-21/-24/-25/-26); with high-endurance local storage (minimum 256 GB) recording motion-based vehicle/person events. Cloud uploads limited to compressed event snapshots (gate-open and arm-displacement events); duplicate-trigger filtering configured to control cellular usage. Remote video viewing on demand only.

4.7 Cloud Platform, Information Security and Privacy The hosted management platform shall be FedRAMP authorized (Moderate or as determined by VA) or receive a VA Authority to Operate before hosted image or user-data features are activated. Until approved by the Information System Security Officer (ISSO) and Privacy Officer (PO), hosted image features shall remain disabled. All data, images and logs generated under this contract are VA records and VA property; the Contractor shall not use, sell or disclose them, and shall return or destroy them at contract end as directed by the CO. Contractor shall comply with VA Handbook 6500.6 and the security clauses incorporated in the contract. User access to the platform shall be limited to VA-designated personnel with unique accounts and multi-factor authentication.

4.8 Commissioning, Testing and Training Submit an Acceptance Test Plan 10 days before testing. Test every status contact, relay command, position feedback, arm-displacement trigger, camera event capture and upload, local recording and playback, power-loss/restoration behavior, communication loss and recovery, hold-open schedules, wireless coverage, and PACS-to-gate release at each location, witnessed by the COR and VA Police. Provide two (2) on-site training sessions (up to 4 hours each) for VA Police Service and Facilities Management on gate operation, manual release, event review, and requesting service; provide as-built drawings, O&M manuals, programming records and password/credential turnover.

4.9 Warranty Minimum one (1) year parts and labor warranty on the complete installed system (gate system and JCI-installed PACS equipment) beginning on the date of Government final acceptance. All manufacturer warranties (e.g., 2-year operator warranties) shall be passed through to VA.

5. MANDATORY SUBCONTRACT — JOHNSON CONTROLS, INC. (PIV BADGE READERS) The VA Police Service PACS at the Washington DC VAMC is a Johnson Controls / Software House C CURE 9000 system with iSTAR-family controllers, installed and supported by Johnson Controls, Inc. To preserve system integrity, warranty and cybersecurity accreditation of that system, the following requirements apply: Subcontract required. The prime Contractor shall subcontract with Johnson Controls, Inc. (JCI) to furnish, install, program, test and commission ALL NEW badge readers and associated access-control hardware at each of the 19 gate locations. Offerors shall submit with their quote a JCI quotation or letter of commitment identifying the scope and price of the JCI work. The prime remains fully responsible to VA for JCI performance, schedule, and warranty. Readers. PIV/PIV-I credential readers listed on the GSA FIPS 201 Approved Products List, OSDP v2 secure channel, mounted on gooseneck pedestals at driver height (dual-height where trucks use the lane), compatible with the existing C CURE 9000 PIV authentication (FICAM) configuration. Controllers and communications. Software House iSTAR-family (or JCI-approved compatible) field controllers, enclosures, power supplies with battery backup and surge protection; communications path to the PACS head-end as approved in writing by VA OIT/ISSO and VA Police Service. Gate integration. Valid credential reads shall release the associated gate through a dry-contact interface coordinated between JCI and the prime; gate position and fault signals shall be made available to the PACS where supported. VA Police control. Upon completion, VA Police Service shall be able, from the C CURE workstation, to grant/revoke parking access by credential, set access levels and schedules by lot, lock down or hold open any gate, and view reader/door event history. Personnel. JCI technicians shall be factory-certified on C CURE 9000/iSTAR and shall meet the background investigation and privileged-access requirements for work on a VA network-connected security system. Service. For each option period exercised, the JCI subcontract shall include maintenance, firmware updates and repair of the readers and controllers installed under this contract.

6. SERVICE AGREEMENT (BASE YEAR + FOUR OPTION YEARS) The service agreement begins on the date of final acceptance of the installation and continues through the base period and each option period exercised by the Government. It covers all 19 gates and all equipment installed under this contract.

6.1 Preventive Maintenance (PM) Quarterly PM at each gate per manufacturer schedules, including UL 325 entrapment-device testing, battery load testing, arm/flange/sensor inspection, radar detector alignment, camera and storage health, and firmware review. Provide a written PM checklist per gate to the COR within 5 business days of each PM cycle.

6.2 Remote Monitoring Automated 24/7 monitoring of gate fault, communication-loss and arm-displacement alerts. Contractor shall review each alert and begin remote troubleshooting within 2 hours (business hours) or by 9:00 a.m. the next business day (after hours), and notify the COR/VA Police of any gate not restored remotely.

6.3 Corrective Maintenance and Response Times PriorityConditionOn-site responseRestore / make safe EmergencyGate stuck closed blocking emergency vehicle route, or stuck open where VA Police declare a security need; safety hazard4 hours, 24/7/365Make safe / manual mode within 4 hours; restore within 24 hours UrgentGate inoperable but alternate access availableNext business dayWithin 2 business days (parts permitting) RoutineDegraded function (camera, LED, single sensor)Within 3 business daysWithin 5 business days Failures from normal wear, defects and equipment age are covered under the firm-fixed price (labor and parts) during warranty and under the service agreement thereafter. Damage from vehicle strikes, vandalism or acts of God is repaired under the Corrective Labor and Repair Parts CLINs at the fixed hourly rate and contract parts pricing, only after COR approval of a written estimate (emergency make-safe excepted).

6.4 Subscriptions and Data Services All cloud platform, monitoring, user, device and cellular data subscriptions required for system operation are included at a fixed annual price for each period. No surcharges, data overages or price increases are permitted except as priced in the option periods.

6.5 Performance Standard Monthly system availability of at least 98% per gate (excluding approved PM windows and damage caused by others). The Contractor shall report monthly availability, alerts, response times and repairs to the COR.

7. PERIOD OF PERFORMANCE AND SCHEDULE PeriodEstimated dates (adjust to award)Content Base Year02/01/2027 — 01/31/2028Installation complete within 120 calendar days after Notice to Proceed; JCI reader integration; warranty; service agreement and subscriptions from acceptance Option Year 102/01/2028 — 01/31/2029Service agreement, subscriptions, JCI reader maintenance Option Year 202/01/2029 — 01/31/2030Same as Option Year 1 Option Year 302/01/2030 — 01/31/2031Same as Option Year 1 Option Year 402/01/2031 — 01/31/2032Same as Option Year 1 MilestoneDue Kick-off meeting (prime, JCI, COR, VA Police, OIT/ISSO, Safety)Within 10 days of award Site survey report, submittals (product data, shop drawings, NDAA certifications, FedRAMP/ATO evidence), installation schedule & traffic planWithin 30 days of award Installation start (after submittal approval)Per approved schedule Acceptance testing and trainingWithin 120 days of NTP As-builts, O&M manuals, credential turnoverWithin 15 days after acceptance

8. HOURS OF WORK, ACCESS AND COORDINATION Normal work hours: Monday Friday, 7:00 a.m. 3:30 p.m., excluding Federal holidays. Work outside these hours requires 48-hour advance COR approval. Emergency service is 24/7. Contractor personnel shall check in with VA Police Service, wear VA-issued or company photo identification, and follow traffic-control plans meeting the MUTCD. Utility locates are required before any excavation or anchoring. The Contractor shall maintain at least one functioning entry and exit per parking area during working hours or provide manual operation coordinated with VA Police.

9. CONTRACTOR PERSONNEL SECURITY Contractor and subcontractor personnel shall complete background investigations at the risk level designated by the VA Position Designation Tool (anticipated Tier 1 / Low Risk for gate technicians; higher for JCI personnel with privileged PACS access) per VA Directive and Handbook 0710. Personnel requiring access to VA information or systems shall complete VA Privacy and Information Security Awareness and Rules of Behavior training before access and annually thereafter.

10. SAFETY, CODES AND STANDARDS UL 325 (Door, Drapery, Gate, Louver and Window Operators and Systems) and ASTM F2200 (Automated Vehicular Gate Construction) NFPA 70, National Electrical Code; OSHA 29 CFR 1910 and 1926; lock-out/tag-out FIPS 201-3 and GSA FIPS 201 Approved Products List; OMB M-19-17 (FICAM) VA Handbook 6500.6 (Contract Security); VA Directive 0730 (Security and Law Enforcement); VA Physical Security and Resiliency Design Manual FAR 52.204-25 (Section 889) and FAR 52.204-23/-27 prohibitions; Buy American / Trade Agreements as determined by the CO Manufacturer installation instructions

11. GOVERNMENT-FURNISHED ITEMS AND RESPONSIBILITIES Existing 120 VAC power at each location; access to sites with escort as required; VA Police PACS administrator support; VA OIT/ISSO review of PACS communications and cloud security documentation; designation of COR and alternate.

12. DELIVERABLES #DeliverableDueTo 1quotation / letter of commitment (with offer)With quoteCO 2Site survey report; installation schedule; traffic plan30 days after awardCOR 3Submittals incl. NDAA 889 and FIPS 201 APL certifications; FedRAMP/ATO evidence for cloud platform30 days after awardCOR / ISSO 4Acceptance Test Plan; completed test reports10 days before test / at testCOR 5As-built drawings, O&M manuals, programming & credential turnover15 days after acceptanceCOR 6Quarterly PM checklists per gate5 business days after each PMCOR 7Monthly performance report (availability, alerts, response, repairs)10th day of following monthCOR 8Written estimates for damage repairsBefore work (except make-safe)COR

13. PERFORMANCE REQUIREMENTS SUMMARY Performance objectiveStandardAcceptable quality levelSurveillance Installation completeAll 19 gates and readers acceptedWithin 120 days of NTPCOR inspection / test witness Preventive maintenanceQuarterly PM at every gate100% completed and documentedPM checklist review Emergency responseOn site within 4 hours95% of callsCall log / VA Police records System availability98% per gate per month98%Monthly report; platform data Remote alert reviewWithin 2 business hours95% of alertsPlatform audit log