Opportunity

SAM #W911KB27RWP14

USACE Alaska District seeks industry input on Wake Island water infrastructure and modular housing projects

Buyer

W2SN ENDIST Alaska

Posted

November 18, 2026

Respond By

December 03, 2026

Identifier

W911KB27RWP14

NAICS

237110, 237990

USACE’s Alaska District is seeking industry input on three construction projects at Wake Island. - Government buyer: U.S. Army Corps of Engineers (USACE), Alaska District. - Project requirements: - WAK030: Replace aging finished-water storage and associated potable-water system components. - WAK032: Repair and improve water-supply and backup-power infrastructure to strengthen reliability and resilience. - WAK033: Replace modular housing to increase on-island bedspace; the project is intended to inform similar future construction. - Estimated acquisition magnitude: $71 million across the three projects. - OEMs and vendors: None are named; no specific products, part numbers, or quantities are provided. - Notice status: This is a market-research RFI, not a solicitation or request for proposal.

Description

REQUEST FOR INFORMATION (RFI) / MARKET INTELLIGENCE NOTICE

Notice: This is a Request for Information (RFI) for market intelligence and for informational purposes only. This announcement does not constitute a Solicitation or a Request for Proposal (RFP), and no solicitation is currently available. Participation in this RFI is strictly voluntary. The Government will not be obligated to award any agreement or contract because of this RFI, nor will it reimburse respondents for any costs associated with the preparation or submission of information. Submitting a response will not affect a firm’s ability to submit a proposal should a formal solicitation be issued in the future.

NAICS Code: 237110- Water and Sewer Line and Related Structures Construction and 236220 – Commercial and Institutional Building Construction (Note: While Other Transaction Authority is not subject to FAR-based small business regulations, this NAICS code is provided for market research to help the Government understand the size and demographics of the interested industrial base.)

Small Business Size Standard: $45 Million

PROJECT OVERVIEW The U.S. Army Corps of Engineers (USACE), Alaska District, has multiple requirements for:

Wake Island Water Tanks(WAK030): Replace aging finished-water storage infrastructure and associated potable-water-system components to provide reliable, resilient finished-water storage and distribution capability for Wake Island operations.

Wake Island Infrastructure Repairs (WAK032): Repair and improve critical utility infrastructure to increase the reliability, resiliency, and operability of Wake Island water-supply and backup-power systems.

WAK033- Wake Modular Housing (WAK033): Improve available on-island bedspace by repairing through replacement modular housing units that support installation personnel and mission requirements. Will be used as a model/prototype for future similar construction.

Estimated Acquisition Magnitude: $71,000,000.

Planned Acquisition Strategy: Anticipated to utilize Progressive Design Build via Other Transaction Authority (OTA)

The Alaska District is conducting market intelligence to assess industry capability and interest in supporting this effort utilizing an Other Transaction (OT) Agreement under the authority of 10 U.S.C. § 2808a, Facility Construction or Repair: Transactions Other Than Contracts and Grants. This authority is distinct from the Department of Defense prototype OT authorities commonly associated with 10 U.S.C. § 4021 and 4022. This authority is intended for military construction projects that involve testing and experimentation associated with new and emergent construction technologies to achieve potential benefits such as enhanced mission resilience, improved installation support, or cost and schedule reduction. The anticipated delivery method is Progressive Design Build.

Phase 1: Design and Pre-Construction Services - The OT Awardee shall assist the Government collaboratively in achieving its goals with respect to the project’s scope, constructability, budget, quality, schedule, and in coordination with the Designer of Record (DOR). Phase 2: Final Design and Construction - Upon reaching an agreed-upon level of design (e.g., 95 to 100%), the Awardee will propose a Guaranteed Maximum Price (GMP). If the GMP is accepted, the Government will exercise construction execution. If a GMP cannot be agreed upon, the Government retains an "off-ramp" to complete the construct the facility via alternative methods.

SUBMISSION INSTRUCTIONS: Please see the following link to the Market Intelligence Questionnaire: https://forms.osi.apps.mil/r/BnKcje1rVx  Submit your responses in MS Forms by 03 December 2026 at 14:00 Alaska Time. Any questions regarding the requirements or issues please reach out to Brittney Morrison at Brittney.Morrison@usace.army.mil , Nicole Thomas Nicole.R.Thomas@usace.army.mil, Theresa Afrank at Theresa.M.Afrank@usace.army.mil and Raven Donelson at Raven.S.Donelson@usace.army.mil. 

Additional Links:MS Forms Questionnaire Link

View original listing