Opportunity
Federal Register #2026-23395
NRC Confirmatory Order Requires TRISO-X to Address TX-1 Construction Quality Issues
Buyer
Nuclear Regulatory Commission
Posted
November 17, 2026
Identifier
2026-23395
The U.S. Nuclear Regulatory Commission issued a Confirmatory Order to TRISO-X, LLC concerning construction quality at its TX-1 process building. - Government agency: U.S. Nuclear Regulatory Commission (NRC); no sub-agency or office is identified. - Named organization: TRISO-X, LLC, the company subject to the order; it is not identified as an OEM or procurement vendor. - Issue: The order addresses an apparent violation involving controls to maintain the design basis for the building’s structural stability, including nonconforming braced-frame intersection welds. - Required corrective actions: Demonstrate that existing welds meet applicable structural requirements; strengthen design controls and construction oversight; conduct inspections and effectiveness reviews; benchmark industry practices; and provide nuclear safety culture training. - Procurement status: This is a regulatory notice, not a solicitation or award. No products, services, quantities, or part numbers are requested.
Description
The Nuclear Regulatory Commission issued a Confirmatory Order to TRISO-X, LLC following successful Alternative Dispute Resolution mediation. The Order concerns an apparent violation related to maintaining the design basis for the structural stability function of the TX-1 process building’s main force resisting system during construction. TRISO-X committed to corrective actions, including actions addressing weld design and quality controls, construction oversight, and training. The Order makes those commitments legally binding and resolves the apparent violation without further NRC enforcement action.