Opportunity
SAM #REQUIREMENTS-26-3483
Award for emergency jetting and restoration of NOAA Sandy Hook seawater intake line #2
Buyer
DEPT OF COMMERCE NOAA EAD-NORFOLK-SAP
Posted
October 05, 2026
Identifier
REQUIREMENTS-26-3483
NAICS
238910, 237110
NOAA’s Sandy Hook laboratory requires urgent restoration of its seawater intake line to support research and marine animal care. - Award and buyer - The Department of Commerce, through NOAA and the National Marine Fisheries Service (NMFS), is responsible for the work at the James J. Howard Marine Sciences Laboratory in Sandy Hook, New Jersey. - Caldwell Marine International LLC is identified in the attached single-source determination as the sole-source provider. - Work required - Inspect and clear obstructions from seawater intake line #2, an existing 6-inch Schedule 80 PVC line. - Provide mobilization, inspection, specialized marine jetting and flushing, and restoration of the line’s functionality. - The service quantity is listed as one; no product purchases or part numbers are specified. - The contractor is responsible for labor, supervision, equipment, tools, materials, logistical support, and marine vessels, as well as applicable safety and environmental controls, testing, demobilization, and site restoration. - Schedule and urgency - Work must begin within 15 days of award and be completed no later than 30 days after award. - The determination says the laboratory had no operating seawater intake lines, creating urgency for research and marine animal care. - Value and products - The provided information does not state the award value. A rough planning estimate is $25,000–$100,000; this is not a reported contract amount. - No OEMs, branded products, or product line items are identified.
Description
The National Marine Fisheries Service (NMFS) James J. Howard Marine Sciences Laboratory, located at Highlands, NJ, relies on continuous, uninterrupted seawater delivery to support critical marine research, aquaculture, and experimental habitats. The existing 6-inch Schedule 80 PVC seawater intake lines have experienced operational constraints, requiring immediate targeted intervention on line #2. The objective of this contract is to safely mobilize, inspect, and perform specialized jetting operations in an effort to clear obstructions and restore functionality within seawater intake line #2.
The Contractor shall provide all labor, supervision, materials, equipment, tools, logistical support, and marine vessels necessary to complete the inspection and targeted obstruction clearance of seawater intake line #2.
The scope is divided into the following primary tasks:
Task 1: Mobilization, Logistics, and Site Preparation:
Marine & Land Mobilization: Mobilize all necessary workboats, dive support vessels, jetting equipment, and support tools to the James J. Howard Marine Lab waterfront. Safety & Environmental Controls: Implement appropriate safety barriers and environmental controls to protect the local marine environment and conform to Sandy Hook's strict environmental regulations.
Task 2: Inspection and Assessment:
Line Inspection: Conduct a thorough initial inspection of seawater intake line #2 to locate, identify, and assess the nature of the internal obstructions. Reporting: Document findings and coordinate with the onsite technical representative prior to or during jetting operations.
Task 3: Jetting and Obstruction Clearance Operations:
Jetting Operations: Deploy specialized marine jetting equipment into seawater intake line #2. Obstruction Clearance: Execute targeted jetting operations in a safe manner in an effort to dislodge, clear, and flush out the identified obstructions to restore line flow.
Task 4: Post-Jetting Testing and Verification:
Flow Verification: Perform functional flow or vacuum testing on line #2 following jetting operations to evaluate the success of the clearance efforts and verify restored operational capacity.
Task 5: Demobilization and Site Restoration:
Demobilization: Remove all boats, equipment, unused materials, and temporary safety barriers from the facility and surrounding waters. Site Restoration: Restore any disturbed land, dock, or staging areas to their pre-work conditions.