Opportunity
SAM #6973GH-26-Q-00131_ASR-9_Beacon_Cable_Kits
FAA Solicitation for ASR-9 Beacon Cable Conversion Kits and Components
Buyer
Federal Aviation Administration
Posted
August 26, 2026
Respond By
September 11, 2026
Identifier
6973GH-26-Q-00131_ASR-9_Beacon_Cable_Kits
NAICS
334419, 334511, 334290, 334418
The Federal Aviation Administration (FAA) is seeking conversion kits for ASR-9 radar facilities to support upgrades to the Air Traffic Control Beacon Interrogator (ATCBI-5) configuration. - Government Buyer: - Federal Aviation Administration (FAA), 6973GH Franchise Acquisition Services office - OEMs and Vendors: - Andrew an Amphenol Co. - Pasternack - Products Requested: - Heliax 1/2" LDF4-50A Upper Cable (Part Number: LDF4-50A), 200 feet - Upper Cable Connectors (Part Number: L4TNM-PSA), 18 units - AVA5-50 Male Connector (Part Number: 78EZNM), 3 units - AVA5-50 Female Connector (Part Number: 78EZNF), 3 units - Lower Cable AVA5-50 100 ft (Part Number: AVA5P-50-C), 350 feet - Surge Arrestor for 0-3 GHz (Part Number: PE73SP1039), 3 units - Services Requested: - Fabrication and delivery of ASR-9 Beacon Cable Conversion Kits, including one first article unit and up to nineteen production units after approval - Unique Requirements: - First article unit required for verification before production - All parts must be compatible with ASR-9/ATCBI-5 radar sites and support integration with the Radar System Replacement (RSR) Program and Brand-New Air Traffic Control System (BNATCS) - All labor, facilities, equipment, and materials must be provided as outlined in the scope of work - Notable Details: - All requested parts are specified in the attached parts list - Emphasis on OEMs Andrew an Amphenol Co. and Pasternack for cable and connector components
Description
1. BACKGROUND
The Federal Aviation Administration (FAA) has identified a requirement to procure conversion kits to support modifications to the Air Traffic Control Beacon Interrogator (ATCBI-5) configuration at Airport Surveillance Radar Model 9 (ASR-9) facilities as part of the Brand-New Air Traffic Control System (BNATCS) implementation under the Radar System Replacement (RSR) Program.
The rotary joints currently installed at ASR-9/ATCBI-5 sites do not provide the number of signal paths required to support integration with the RSR architecture. To achieve compatibility, the existing rotary joints must be converted to the configuration utilized at ASR-9 sites equipped with the Mode Select Beacon System (Mode-S). This conversion requires the installation of a kit developed by AJW-1433, which replaces the existing beacon cables.
2. CONTRACTING OFFICER’S REPRESENTATIVE (COR):
The COR formally designated this responsibility by the Contracting Officer to provide direction and Government oversight to the contractor on matters related to this contract. The COR is:
Brandon Brumley
AJW-L910, Radar Technical and Program Support Branch
3. SCOPE OF WORK
The contractor must furnish all labor, facilities, equipment, and materials to fabricate a kit as outlined in each section that follows.
A. CLIN 001 – One (1) First Article Unit - Shall be delivered 90 days After Receipt of Order
B. CLIN 002 – Option to purchase up to nineteen (19) Production Units after first article approval
4. REQUIREMENTS
4.1 Design, Construction, and Testing
The contractor shall procure and package the parts listed in Attachment 1 – Parts List into a Kit.
4.2 First Article Unit Delivery
Contractor must deliver one verification unit. Delivery shall occur no later than (NLT) ninety (90) days at receipt of order (ARO).
4.3 Verification Unit Analysis
Upon receipt of first article unit, FAA shall perform visual inspection to determine conformance to Attachment 1 – Parts List. FAA will have 30 days to accept or reject first articles.
4.4 Production Units
Once approval is provided for the first article unit, the contractor shall be considered an approved source of production units. The number of units for production is nineteen (19). Delivery of production units shall occur NLT 180 days after notification of First Article Approval.
5. PREPARATION FOR DELIVERY
5.1 Preservation, Packaging, and Packing
Preservation, packaging, and packing shall be IAW Provision 61.