Opportunity

Santa Clarita Valley Water Agency PlanetBids #CIP27-1026 Task 3

SCVWA Friendly Valley Tank 4 Coating and Lining Replacement Project

Posted

August 18, 2026

Respond By

September 29, 2026

Identifier

CIP27-1026 Task 3

NAICS

238320

This opportunity involves maintenance and rehabilitation of the Friendly Valley Tank 4, an 80-foot diameter welded steel water storage tank managed by the Santa Clarita Valley Water Authority (SCVWA). - Government Buyer: - Santa Clarita Valley Water Authority (SCVWA) - Contact: James Saenz - Scope of Work: - Remove and replace the exterior paint system of the tank within 4-6 years - Cleaning per SSPC SP-6 - Application of 4-6 mils industrial epoxy primer - Application of 3-5 mils polyurethane finish coat - Remove and replace the interior epoxy lining within 2-3 years - Cleaning per SSPC SP-10 - Application of three 4-6 mil coats of NSF Certified epoxy lining - Underwater repair of aggressive rust spots below the waterline using NSF certified underwater curing epoxy - Products/Services Requested: - Exterior paint system removal and replacement - Interior epoxy lining removal and replacement - Underwater rust spot repair epoxy - Unique Requirements: - All coatings and linings must be NSF Certified for potable water use - Surface preparation must meet SSPC SP-6 (exterior) and SSPC SP-10 (interior) standards - Work must be completed within recommended timeframes (interior: 2-3 years, exterior: 4-6 years) - No specific OEMs or vendors are named; the solicitation is open to qualified contractors with experience in water tank coatings and linings.

Description

This project involves spot repair and overcoat painting of the exterior paint system and complete interior relining of the Avenue of the Oaks Tank 2. The scope includes removal and replacement of all existing interior linings, exterior paint repair through spot repairing and overcoating with epoxy and urethane paint systems, surface cleaning, debris containment and disposal, application of polyurethane caulking between the tank and concrete ring wall, and cleaning and disinfection of the tank after curing of the interior lining. The work must comply with applicable federal, state, and local requirements. Bidders must submit bids electronically and provide physical bid security by the due date.

View original listing