Opportunity

SAM #FA822426Q0003_1

Installation of Government-Furnished Ingersoll Rand Compressors and Cooling System at Hill AFB

Buyer

Fa8224 OLH PZI PZIM

Posted

July 16, 2026

Respond By

August 04, 2026

Identifier

FA822426Q0003_1

NAICS

238220, 238290

This opportunity is for the installation and integration of government-furnished Ingersoll Rand air compressors and cooling equipment at Hill Air Force Base, Utah. - Government Buyer: - Air Force Materiel Command, Air Force Sustainment Center, FA8224 office at Hill AFB, Utah - OEMs and Vendors: - Ingersoll Rand (primary OEM for compressors, dryers, and glycol coolers) - Products/Services Requested: - Installation of two government-furnished Ingersoll Rand compressors, dryers, and glycol coolers - Contractor to provide all labor, tools, and standard materials (e.g., piping, wiring, epoxy) - Connection of equipment to 460V power and base air loop in Building 269 - Unique/Notable Requirements: - All primary machinery is Government Furnished Property (GFP); no product procurement required - Facility drawings are Controlled Unclassified Information (CUI) and require vetted SAM.gov access - Davis-Bacon prevailing wage requirements apply - Strict completion deadline to preserve manufacturer warranty

Description

The Air Force is soliciting a 100% Small Business Set-Aside for a contractor to install and integrate a Government-furnished compressor and cooling system at Hill AFB, Utah.

Key Project Details:

The Work: The contractor will provide the labor, tools, and standard materials (piping, wiring, epoxy) to physically install two government-owned Ingersoll Rand compressors, dryers, and glycol coolers into Building 269 and connect them to the base's 460V power and air loop. The Constraints: All primary machinery is Government Furnished Property (GFP). Facility drawings are Controlled Unclassified Information (CUI) requiring vetted SAM.gov access. Davis-Bacon prevailing wages apply. Critical Deadlines:

<ul>
    <li>
    <p><strong>Site Visit RSVP Deadline:&nbsp;</strong>20 July 2026</p>
    </li>
    <li>
    <p><strong>Pre-Quote Site Visit:</strong>&nbsp;23 July 2026</p>
    </li>
    <li>
    <p><strong>Contractor Q&amp;A Deadline:</strong> 27 July 2026</p>
    </li>
    <li>
    <p><strong>Quotes Due:</strong>&nbsp;04 August 2026</p>
    </li>
    <li>
    <p><strong>Mandatory Completion:</strong>&nbsp;On or before 17 August 2026 (Strict deadline to preserve the manufacturer&#39;s warranty).</p>
    </li>
</ul>
</li>