Opportunity

SAM #19AU9026Q0010

Reconstruction of Basketball Half-Court at U.S. Embassy Vienna Marine House

Buyer

U.S. Embassy Vienna

Posted

June 11, 2026

Respond By

July 29, 2026

Identifier

19AU9026Q0010

NAICS

238910, 238990

This opportunity is for the reconstruction of the basketball half-court at the U.S. Embassy Vienna Marine House, managed by the Department of State. - Government Buyer: - U.S. Department of State - U.S. Embassy Vienna - Scope of Work: - Demolition and removal of existing sports field surface, substructure, exterior lights, and basketball basket with posts - Soil removal and disposal - Construction of a new sports field surface and substructure - Installation of an EPDM rubber surface or equivalent - Installation of a new adjustable basketball hoop - Installation of two new exterior lights with cabling - Laying stone slabs around the court perimeter - Painting of court lines - Final cleaning of the site - Unique/Notable Requirements: - Contractor must comply with U.S. Government security regulations, including clearance for employees, vehicles, and materials - Work must be performed while the facility remains operational, with minimal disturbance to residents - Safety and protective measures are required throughout the project - No specific OEMs, vendors, or part numbers are specified in the solicitation

Description

This project if for the reconstruction of the basketball half-court at the U.S. Embassy Vienna Marine House, located in 1190 Vienna.

The existing outdoor basketball half-court is at the end of its life cycle and too small in dimensions.

The scope of work includes but is not limited to the demolition of the existing sports field surface and substructure, in their entirety, as well as the removal of the lighting.

Construction of a new sports field surface, including the substructure, in its entirety, as well as a new lighting system.

Scope of work: General Contractor for Construction of Sport Fields and Electrical Installation

- Site Installation

- Demolition

Demolition, removal and disposal of existing basketball half- court (asphalt layer 7x8m), existing exterior lights and basketball basket with posts  Soil removal and disposal for new basketball half- court dimension (13mx14m = 182m²), 0.3m depth = ~55m³

- Construction of a new sport field

Preparation/installation subgrade/subbase incl. drainage Installation top layer (EPDM rubber surface or equal) Installation point foundation for 1 basketball hoop and for 2 light poles Installation 1 adjustable basketball hoop, and 2 exterior lights incl. cabling/rewiring Laying stone slabs 40x40x5cm around the court Painting lines Final cleaning

- Special requirements

The work will be carried out while the facility remains in operation and in the presence of the residents, who should not be disturbed during the construction work USG Security regulations Clearance process for employees, cars, material on site Safety and protective measures

Execution periods

Indicative construction schedule: 5 weeks in fall 2026