Opportunity
SAM #f8a710f5a12a4e77a5b38189f303ae04
DOE Clarifies Site Information and Applicant Responsibilities for RFA #: DE-FOA-0000001
Buyer
Department of Energy
Posted
June 02, 2026
Respond By
May 28, 2026
Identifier
f8a710f5a12a4e77a5b38189f303ae04
NAICS
562910, 237990
This notice provides clarifications from the Department of Energy (DOE) regarding RFA #: DE-FOA-0000001. - DOE will supply the selected applicant (Selectee) with existing site information, including as-built data, plans, and site characterization details. - The Selectee is responsible for all site characterization activities required for licensing, permitting, construction, and upgrades. - No specific products, services, vendors, or procurement opportunities are announced in this notice. - The referenced site is the INTEC site, with the place of performance in Richland, Washington. - No OEMs, part numbers, or contract values are provided. - No service or product line items are listed. - No period of performance details are specified. - No competing vendors or products are identified.
Description
DOE responses for RFA #: DE-FOA-0000001 T
These are the second round of responses to questions due Midnight May 27, 2026 after the site tour.
Question #1
For the "Potential Location" referenced in Figure 1 of the RFA:
Have any structures previously been built in this site area, and if yes - what were the structures? What is the anticipated depth of rock below grade in this site area?
Answer 1 (reference RFA page 9): DOE will provide to the Selectee existing information related to the specific site. Site characterization to support activities such as licensing, permitting, construction and upgrades are the responsibility of the Selectee.
Question #2
Can the government provide any as-built information or plans relating to buildings, utilities, and/or paved roads on the INTEC site currently?
Answer 2 (reference RFA page 9): DOE will provide to the Selectee existing information related to the specific site. Site characterization to support activities such as licensing, permitting, construction and upgrades are the responsibility of the Selectee.
Question #3
Can the government provide any information relating to utilities or abandoned-in-place infrastructure that exist below the surface of the site?
Answer 3 (reference RFA page 9): DOE will provide to the Selectee existing information related to the specific site. Site characterization to support activities such as licensing, permitting, construction and upgrades are the responsibility of the Selectee.
Question #4
Can the government provide any site characterization data for the INTEC site or surrounding areas?
Answer 4 (reference RFA page 9): DOE will provide to the Selectee existing information related to the specific site. Site characterization to support activities such as licensing, permitting, construction and upgrades are the responsibility of the Selectee.