This opportunity involves the replacement of a major HVAC system at McConnell Air Force Base, Kansas: - Government Buyer: - U.S. Air Force, Kansas Air National Guard, McConnell Air Force Base - Contracting office: W7M9 USPFO ACTIVITY KSANG 184 - OEMs and Vendors: - Trane (specified as the manufacturer for both chiller and air handling unit) - Products/Services Requested: - Removal and disposal of existing 40-ton air cooled chiller and air handling unit (AHU) - Furnishing, installation, and commissioning of a new 40-ton Trane air cooled chiller - Furnishing, installation, and commissioning of a matching 40-ton Trane AHU - Update of Direct Digital Control (DDC) system for compatibility - Expansion of concrete pad with reinforced 4000 psi concrete if required - Electrical panel and breaker updates as needed - Use of a crane for equipment removal and installation - Unique/Notable Requirements: - All new equipment must use 134A refrigerant or equivalent - Equipment must be compatible with existing building automation systems - Contractor must comply with federal, state, and local codes, and manage hazardous materials per DoD and base requirements - Safety and site access protocols must be followed - Proper grounding and electrical compatibility are required
Description
This is a SOURCES SOUGHT ANNOUNCEMENT ONLY. The purpose of this sources sought is for market research to gain knowledge of potential sources for future needs including interested small business sources. This notice is for planning purposes only. All interested parties should respond.
Kansas Air Nationl Guard, McConnel AFB, Kansas, will soon be soliciting for a project for Building 42 Chiller Replacement Work shall consist of the following: Safely dismantle, remove, and dispose of the existing 40 ton air cooled chiller, refrigerant, and air handling unit (AHU), and furnish, install, and commission a new 40 ton air cooled Trane chiller and matching Trane AHU to restore optimal environmental controls, utilizing 134A refrigerant or equivalent. Contractor to ensure new units are properly grounded. This project may require the contractor to utilize a crane to remove and replace the units. Update Direct Digital Control (DDC) system as necessary to correspond with new chiller unit. The existing chiller is set on a concrete pad northwest of Building 42 that can be reutilized if the new unit final dimensions match the current size of the existing unit, otherwise it will be the responsibility of the contractor to expand the pads as needed. Electrical will be available and it is the contractor’s responsibility to ensure all panels / breakers are updated to meet the standards of the new chiller unit. Current power is 460V with 500 kcmil conductors. New unit will utilize this electrical connection and voltage. Equipment specifications:
Trane air cooled chiller – 40 ton cooling capacity, high efficiency scroll or rotary compressor design, factory mounted controls compatible with existing building automation systems. Trane AHU – Matched 40 ton capacity, variable frequency drives for supply and return fans, customized modular design to fit existing mechanical room footprint.
For this requirement, the small business size standard is 19 Million for NAICS 238220. In the event small business contractors are not avaialble for adequate competition for this project, it may be advertised as unrestricted. Complete and return attached sources sought form to include bonding capability and advise on your capabilities and or past perfromance in terms of the projected requested. Include the following email subject line "Sources Sought B42 Chiller Replacement" when emailing, to 184WG.MSG.CONTRACTING@us.af.mil. Use the same email address if you have additional questions.