Stormwater Board Meeting 2026-2-11
February 11, 2026
The Greenwood Indiana Stormwater Board held a meeting on February 11, 2026, focusing primarily on procurement and contract management related to stormwater infrastructure projects. The board approved a change order for a bridge project originally started in 2021, increasing the contract price by $46,425.10 to a total of approximately $3 million and extending the substantial completion date by 48 days to January 30, 2023. Additionally, the board approved updates to the stormwater technical manual to comply with an audit by the Indiana Department of Environmental Management (IDEM), including a resolution to amend the manual and a new policy for the use and control of anionic polyacrylamide polymers on construction sites. The meeting also included approval of the claims docket and routine reports, with no new contracts or bids discussed.