# North Carolina Sets Data Center Power Tariffs

The North Carolina Utilities Commission approved rate settlements for Duke Energy Carolinas and Duke Energy Progress, effective January 1, 2027, and established the state’s first dedicated tariff for data centers above 50 MW. Facilities above 100 MW face a 15-year minimum contract and billing demand of at least 75% of contracted capacity; some transmission and stranded-generation charges remain undetermined. For data center developers, large-load operators, and their contractors, these terms affect power-cost forecasts, site selection, and long-term energy contracting.

- The revised utility rates take effect **January 1, 2027**; organizations planning North Carolina operations should account for the new rates and tariff terms in project cost models.
- Operators of facilities above 100 MW should evaluate the 15-year minimum contract and 75% billing-demand floor against expected load, ramp-up schedules, and project financing.
- Transmission and stranded-generation charges are not yet fully determined, so current cost estimates may not capture all tariff-related expenses.

**Jurisdictions:** sled
**Industries:** Energy & Utilities
**Topics:** Policy
**Published:** November 21, 2026

### Government Entities
- North Carolina Utilities Commission (NCUC)
- North Carolina Public Staff

### Vendors
- Duke Energy Carolinas ()
- Duke Energy Progress ()

### Sources
- [North Carolina approves Duke Energy rate hikes, data center rules](https://gcn.com/north-carolina-duke-energy-rate-hikes/23418) - gcn.com