# Project Jupiter Builds New Mexico Data Center Campus

A November 17, 2026 data-center digest reported that Project Jupiter, a 1,000 MW campus under construction near Santa Teresa, New Mexico, has **$18 billion in construction financing**. HSBC reportedly sold a roughly $300 million portion of its financing share; the report also names ING and Société Générale, but its financing details are incomplete. STACK Infrastructure is identified as the project operator. No government solicitation, award, or procurement contact was reported, so this is a private-sector infrastructure development—not an open public bid.

- The campus’s scale may create downstream demand for data-center construction, power, equipment, and related services; suppliers can assess whether their capabilities align with the project’s needs.
- Contractors should distinguish this private financing activity from government procurement and seek confirmed project or subcontracting channels before treating it as a business opportunity.
- The digest also tracked 480 campuses globally and 20.6 GW of capacity under construction, indicating a broader data-center development pipeline relevant to infrastructure suppliers.

**Jurisdictions:** sled
**Industries:** Information Technology, Construction & Infrastructure
**Topics:** Digital Infrastructure
**Published:** November 17, 2026

### Vendors
- STACK Infrastructure (Project operator)
- HSBC (Financing participant; reportedly sold a roughly $300 million portion of its share)
- ING (Financing participant; specific role not clear in the report)
- Société Générale (Financing participant; specific role not clear in the report)

### Sources
- [https://t.co/DrLGfxIQSU
GAI DATA CENTER DEVELOPMENT DAILY DIGEST, TUESDAY, NOVEMBER 17, 2026

LEAD ITEMS

- Project Jupiter, Dona Ana County, New Mexico: HSBC sold its roughly $300 million slice of the $18 billion construction financing in the mid-80s, and ING and Societe General](https://x.com/TheValueist/status/2122841987032502367) - twitter-regulatory