# RHS Building Committee Meeting 10/21/26

The Revere High School Building Committee met on October 21, 2026, to review project invoices, contingencies, schedule, and construction progress. The committee approved invoices for Leftfield ($185,274), Briggs Independent Construction Testing (about $55,664; 72% of its $400,000 budget), Perkins Eastman ($442,750), and Conigley’s September construction requisition 16A (about $10.965 million). A committee member asked for clarification of a credit in the Conigley requisition; the project team agreed to report back. The team also expects to recommend additional funding for construction testing in a future meeting, potentially in December or January.

The committee considered additional geotechnical and vibration monitoring, with the project team presenting a proposed cost of $256,080. A motion to allocate $180,000 for the monitoring services passed, with five votes in favor, four opposed, and one abstention; the team will track the work and report on whether further monitoring is warranted. The project update reported that substantial completion remains 48 days ahead of the contractual date, and that the project has an $18.5 million hard contingency and approximately $14.8 million in GMP savings, subject to the MSBA funding agreement amendment. Construction updates included geothermal field work, concrete pours, and ongoing structural-steel erection.

**Jurisdictions:** sled
**Industries:** Construction & Infrastructure, Education
**Topics:** Physical Infrastructure
**Published:** October 21, 2026

### Sources
- [RHS Building Committee Meeting 10/21/26](https://www.youtube.com/watch?v=LqNHKYPN9Kg) - RevereTV