# Saskatchewan Tenders #CSD-FOXV-261126

Fox Valley School mechanical upgrades: boilers, pumps, controls, and HVAC alternates

**Posted:** November 27, 2026
**Respond By:** December 17, 2026
**Identifier:** CSD-FOXV-261126
**NAICS:** 238220, 333414

Chinook School Division is seeking mechanical contractors to upgrade heating and ventilation systems at Fox Valley School in Saskatchewan.
- **Buyer and project:** Chinook School Division No. 211; Fox Valley School Mechanical Upgrades, Project 26089. HDA Engineering Ltd. is identified as the designer.
- **Base work:** Replace boilers, pumps, controls, and related equipment, with associated ductwork, piping, electrical work, and alterations to existing heating and ventilation systems.
- **Named OEMs and key equipment:** **Viessmann** — three 200-W B2HA boilers, 530 MBH input each; **Carrier** — two alternate WeatherMaker 48FCEA04A2A3, 3-ton rooftop units; **Engineered Air** — AHU-1, Model LMD6/C; **Bell & Gossett** — specified pumps, including three PL-100 boiler circulators and two 1.5AD-es main heating pumps. Armstrong is the alternate pump supplier.
- **Other specified equipment:** Axiom Industries DSF100 system feeder and NT-15 neutralization tank; Caleffi SEP4 hydraulic separator, Model NA549082AM; Amtrol 300-L expansion tank; Shelco FOS-786-316-TH-B side-stream filter; Axiom CBF-2 pot feeder; A.O. Smith BTX-80 water heater; Loren Cook exhaust fans; Engineered Air HUH-4 unit heater; Watts LDS-3 valve; and four Bilco T3 floor hatches.
- **Alternates:** Rooftop-unit replacement; replacement of AHU-1, coil pump P-3, and exhaust fan EF-1; and separate pump-supply prices for Bell & Gossett and Armstrong.
- **Electrical and controls:** Includes equipment disconnections and reconnections, new panel work, and expansion and testing of the existing Notifier fire alarm system. Prairie Controls is identified as the controls contractor. Electrical specifications name Schneider, Eaton, and Siemens for panelboards and Square D as a switchboard standard of acceptance.
- **Other named vendors/material manufacturers:** Nexus, Sika, Belanger, Clearline Technology, and Hubbell Kellems. Equipment and controls must be operational at substantial completion; boiler startup is by a factory-trained technician, and the specified heating solution includes 40% inhibited ethylene glycol.

### Description

Chinook School Division No. 211 is seeking bids from qualified mechanical contractors to replace the existing hot water boilers, pumps, controls, and related equipment at Fox Valley School for a stipulated price. Bids must also include alternate prices for replacement of the air handling unit and associated return air fan, and two rooftop units. Substantial completion is required by August 20, 2027. A mandatory site walkthrough is scheduled for December 4, 2026; contractors must notify HDA Engineering Ltd. at least 24 hours in advance.

[View original listing](https://www.sasktenders.ca/Competitions/Print?id=be4aa174-0955-4521-8c9f-95e78743fb46)