The City of Georgetown, Texas, is seeking a Construction Manager at Risk for its new Fire Station No. 8.
- **Buyer and project**
  - Buyer: City of Georgetown, Public Works Department; solicitation managed by the Purchasing Department. Nicole Abrego is identified as the buyer, and Eric Johnson as the Owner’s representative.
  - Project: Fire Station No. 8, CMAR No. 202709, at 1901 Westinghouse Road in Georgetown.
- **Requested services**
  - Preconstruction: project coordination, estimating, scheduling, constructability reviews, value engineering, procurement planning, and preparation of a Guaranteed Maximum Price (GMP) proposal.
  - Construction phase: subcontractor bidding, construction administration, supervision, and delivery of the work under the contract documents.
  - Proposals include separate lump-sum prices for preconstruction and general conditions, plus a CMAR fee percentage.
- **Facility scope and budget**
  - Approximately 12,000–13,025 gross square feet, including staff living, working, and sleeping areas; three pull-through apparatus bays; utilities; site improvements; and related work.
  - Estimated construction budget: $8.7 million. Fire Station No. 7 is a reference point, not a prototype; the new station is not expected to be a pre-engineered metal building.
- **Named firms**
  - **GFF, Inc.** is identified by the latest clarification as the project architect; this supersedes earlier references to Brown Reynolds and Watford. Parkhill is also named as architect in an earlier project document, creating a conflicting reference.
  - Kimley-Horn is mentioned in connection with civil engineering.
- **Notable requirements and planning assumptions**
  - Preconstruction is anticipated to last about nine months; construction is estimated at 365 calendar days, subject to adjustment.
  - Price time-dependent general conditions using a 180-day construction assumption for evaluation; actual duration and costs are to be finalized through the GMP process.
  - No geotechnical report or lot survey was available in the project information reviewed.
  - The agreement excerpt provides for $650 per calendar day in liquidated damages for late Substantial Completion and 5% retainage. Payment and performance bonds are not required with the proposal; security bonding is required from the successful contractor after contract execution.

### Description

The City of Georgetown seeks proposals from qualified respondents to provide Construction Manager at Risk (CMAR) services for construction of a new Georgetown Fire Station No. 8 at 1901 Westinghouse Rd, Georgetown, Texas. The solicitation follows a one-step selection process under Texas Government Code Chapter 2269, Subchapter F, Section 2269.253. Proposals must be submitted electronically through the City E-bid system by December 1, 2026, at 2:30 PM CT. Addendum No. 3 clarifies that GFF, Inc. is the project architect.