The City of Rancho Palos Verdes Public Works Department is soliciting bids for Project No. 8725 to install two bioretention systems on Peninsula Verde.
- **Buyer:** City of Rancho Palos Verdes, Public Works Department, Rancho Palos Verdes, Los Angeles County, California.
- **Scope:** Furnish labor, materials, and equipment to install two stormwater systems that divert runoff from a 26.6-acre tributary area before it reaches Machado Lake. The systems are designed for 24-hour retention capacity of 0.05 acre-feet.
- **Products and materials:** 30 linear feet of 8-inch perforated PVC pipe and fittings; 10 cubic yards of 3/4-inch gravel; 350 square feet of filter fabric; two catch basins; 5 cubic yards of bioretention soil media; 1 cubic yard each of wood mulch and splash rock; and two 8-inch cleanouts.
- **Installation and related work:** Mobilization, traffic control, BMP and erosion control, utility verification and potholing, shoring, 165 linear feet of 8-inch PVC pipe installation, 2 cubic yards of sidewalk replacement, two pipe connections, 85 square feet of planting, and two catch basin stencils.
- **Standards and requirements:** Catch basins reference SPPWC 302-4; pipe connections reference SPPWC 335-2. License requirements are specified in the bid proposal. Liquidated damages are $1,000 per day.
- **OEMs and vendors:** No OEMs, manufacturers, or vendors are identified by name.

### Description

The project involves furnishing labor, materials, equipment, and incidental work to install two bioretention systems on Peninsula Verde. The systems will divert stormwater and urban runoff from a 26.6-acre tributary area before it flows to Machado Lake in Harbor City. They will provide 24-hour retention capacity of 0.05 ac-ft to address water quality needs. The work is described further in the Contract Documents and has a duration of 45 working days.