# Temple Bonfire #Bid #54-01-27

Construction of Knob Creek Basin Trunk Sewer Improvements, Phase III

**Posted:** November 24, 2026
**Respond By:** January 12, 2027
**Identifier:** Bid #54-01-27
**NAICS:** 237110

The City of Temple is seeking a contractor to build the third phase of the Knob Creek Basin trunk sewer improvements in Southeast Temple.
- **Buyer:** City of Temple, Public Works Department — Engineering, Temple, Bell County, Texas.
- **Work requested:** Construct a new sewer trunk line from the Doshier Farm Wastewater Treatment Plant to N 14th Street.
- **Notable requirement:** Include an alternate to bore beneath Avenue H instead of installing that section by open trench.
- **Schedule:** Complete the work within 730 consecutive calendar days after the Notice to Proceed.
- **Estimated project cost:** $8,690,770.
- **OEMs and vendors:** No OEMs or vendors are named.

### Description

Construct a new sewer trunk line through Southeast Temple, from the Doshier Farm Wastewater Treatment Plant to N 14th Street. The project includes an add alternate to bore under Avenue H instead of installing the line by open trench. The selected contractor must complete the work within 730 consecutive calendar days from Notice to Proceed. The estimated cost is $8,690,770.00.

[View original listing](https://templetx.bonfirehub.com/opportunities/264171)