# Carrollton Ionwave #ENG CSP #27-011 Addendum 3

Frankford Road reconstruction with water, drainage, traffic, pedestrian, and landscape improvements

**Posted:** October 26, 2026
**Respond By:** December 02, 2026
**Identifier:** ENG CSP #27-011 Addendum 3
**NAICS:** 237310, 237110

The City of Carrollton is seeking a contractor to reconstruct Frankford Road between Old Denton Road and Standridge Drive, with substantial utility, drainage, traffic, pedestrian, landscaping, and irrigation work.
- **Buyer:** City of Carrollton, Texas — Purchasing Department.
- **Project:** Frankford Road Reconstruction Segment 3, ENG CSP #27-011.
- **Scope:** Roadway reconstruction; water-line and storm-drain work; sidewalks, curb ramps, traffic control and signals; signing, erosion control, landscaping, and irrigation. No sanitary sewer or noise-wall improvements are included.
- **Notable products and OEMs:** **NoTraffic** video detection system at McCoy Road, including three presence-detection sensors; **Tensar NX750 or equivalent** geogrid, 28,000 SY. The bid schedule also includes street-sign, pedestrian-signal, landscaping, and irrigation items.
- **Lighting responsibilities:** Oncor furnishes and installs permanent poles, luminaires, and wiring and removes existing illumination poles. The contractor provides specified conduit and foundations; temporary roadway lighting is not required. The updated bid schedule governs lighting-fixture requirements.
- **Other named organizations/vendors:** Atmos and DART are referenced in the project materials; Evolve’s EACL01 lighting fixture is referenced in a question. NoTraffic and Tensar are named product manufacturers.
- **Selected quantities:** 28,300 SY of reinforced 8-inch roadway concrete pavement; 3,600 LF of 12-inch waterline; 4,150 CY of unclassified excavation; 29 precast pole foundations; and five DART bus-stop pads.
- **Commercial considerations:** Engineer’s estimate is $12,260,900. Proposals are evaluated on price (60%), qualifications/project history (25%), and proposed construction duration (15%). The contractor proposes the duration.

### Description

The City of Carrollton is soliciting proposals for Frankford Road Reconstruction Segment 3. The project includes reconstruction work along Frankford Road from Old Denton Road to Standridge Drive, with plans, specifications, geotechnical data, and addenda provided as bid documents. Electronic submission is preferred, though paper proposals may be accepted by the deadline. A bid bond or cashier’s check for 5% of the total bid is required.

[View original listing](https://carrolltonbids.ionwave.net/PublicDetail.aspx?bidID=509&SourceType=1)