Plano Independent School District is seeking proposals to upgrade HVAC and related systems at Daffron Elementary School in Plano, Texas.
- **Buyer:** Plano Independent School District (Plano ISD), Purchasing Department.
- **Scope:** Replace campus-wide HVAC controls, existing air-cooled chillers, and three rooftop units; provide associated mechanical, electrical, and controls work.
  - **Controls requirement:** Reliable Controls, provided by Enviromatics, is the only acceptable controls manufacturer/vendor.
  - **Alternate No. 1:** Replace one existing make-up air unit, identified as Captive Air, and perform associated work.
  - **Alternate No. 2:** Replace two existing backflow preventers.
- **Additional items:** Visitor signage is anticipated to be a standard post-mounted metal sign and is handled through contingency, not the base bid. An allowance covers replacement of valves, actuators, and strainers.
- **Electrical:** Add one 50A/3P breaker to Panel DP1, two 20A/1P breakers to Panel KH, and one 100A/3P breaker to Panel MS. Breakers must match the existing panels and specifications.
- **Coordination:** Coordinate with the District’s chemical-treatment provider, **Solenis (formerly Chem-Aqua)**.
- **Budget:** The stated project budget is $1,455,000; source summaries differ on whether the $75,000 contingency and $50,000 allowance are included or additional.
- **Period of performance:** Not stated.

### Description

Plano Independent School District is requesting competitive sealed proposals for the Daffron Elementary School Systems and Compliance project. The base bid includes campus-wide HVAC controls replacement, replacement of existing air-cooled chillers and three rooftop units, visitor signage, and associated mechanical, electrical, and controls work. Alternate No. 1 covers replacement of the existing make-up air unit; the Q&A also identifies Alternate No. 2 as replacement of both existing backflow preventers. The stated estimated budget is $1,455,000, with a $75,000 contingency and a $50,000 allowance for replacement of valves, actuators, and strainers.