Miami University is seeking bids to replace the redundant battery-bank systems in Switch House 4 in Oxford, Ohio.
- **Government buyer:** Miami University, Physical Facilities Department, including Facilities Contracting/Strategic Procurement Office and Planning, Architecture, & Engineering.
- **Requested equipment:**
  - **Hoppecke** FNC 176L nickel-cadmium batteries: 184 cells total, with 92 per bank.
  - **Enviroguard** Eagle Series spill-containment units: 2, sized for the provided racks.
  - **HindlePower** ATevo battery chargers: 2, model ATEV1130050F208SS1XB1.
  - Two-tier, two-step seismic battery racks, connectors, jumpers, hardware, leads, and related materials; existing racks may be reused if compatible.
- **Work and requirements:** Replace the banks and chargers in sequence, keeping one redundant bank in service at a time. Reuse existing charger wiring and power where possible, and prepare removed batteries for recycling arranged by the University. Test each system to applicable IEEE, NETA, and manufacturer specifications, including an IEEE 1106-2015 capacity-discharge test; correct deficiencies and retest as needed. Provide operation and maintenance manuals and test reports.
- **Notable conditions:** Ohio prevailing-wage requirements and a 5% EDGE participation goal apply. Proposed alternatives require advance written approval from the University Project Manager.

### Description

Miami University is seeking bids to replace two existing battery banks, chargers, and associated equipment in Switch House 4. The work includes removing and replacing each battery bank and charger sequentially, installing associated equipment and materials, and conducting acceptance and capacity-discharge testing. The specified equipment includes 184 nickel-cadmium batteries, two spill-containment units, and two battery chargers; existing battery racking may be reused if compatible with the new cells. Bids are due electronically through Ionwave by December 1, 2026, at 2:00 PM ET, and the project is subject to Ohio prevailing-wage requirements.