The Illinois Secretary of State’s Chicago West boiler project received a $31,793 change order for revised flue routing and related mechanical work.
- **Government buyer:** State of Illinois, Office of the Secretary of State; Physical Services Department. Buyer contact: Traci Jones-Richardson. Work location: Chicago West Facility, Chicago, Cook County.
- **Vendor:** Voris Mechanical, Inc. No boiler or component OEMs are identified.
- **Change-order work:** One service line item for alternative boiler flue/stack routing and installation, including installation of an 8-inch strainer bypass with butterfly isolation valve, concrete cutting, roofing, and chimney work.
- **Value and schedule:** Proposed contract increase of $31,793. Work is to be completed within 40 calendar days after change-order approval.

### Description

This notice records a change order with Voris Mechanical for the boiler replacement at Chicago West and is explicitly stated not to be a bid opportunity. The change increases the contract by $31,793.00. The work covers alternative boiler flue/stack routing and installation due to unforeseen conditions, including an 8-inch strainer bypass with butterfly isolation valve. The source states that the work is to be completed within 40 calendar days from approval of the change order.