# New York State Contract Reporter #2140553

Franklin Courts phased infrastructure, remediation, and redevelopment construction

**Posted:** November 09, 2026
**Respond By:** December 01, 2026
**Identifier:** 2140553
**NAICS:** 237990, 237110, 237310, 237130, 237210

The Village of Tarrytown is seeking bids for phased infrastructure and redevelopment work at Franklin Courts in Westchester County, New York.
- **Government buyers and project parties**
  - Soliciting office: Village of Tarrytown Engineering Division.
  - Related funding: Westchester County Department of Planning, through its Housing Implementation Fund, will provide up to $5 million toward infrastructure; the total project cost is not stated.
  - Environmental oversight: New York State Department of Environmental Conservation, in consultation with the New York State Department of Health.
  - Named project parties in the attachments include WBP Development, LLC and GEODesign, Inc. P.C.; neither is identified as a bidding vendor in the solicitation.
- **OEMs and products**
  - No OEMs, manufacturers, product models, or product part numbers are identified. This is a construction and services procurement, not a specific equipment purchase.
- **Requested work**
  - Site preparation, excavation, grading, soil management, and removal of approximately 22 underground storage tanks.
  - Stormwater, sanitary sewer, water-main, and electrical utility work; retaining walls; roads, paving, sidewalks, drainage, lighting, signage, and landscaping.
  - Electrical trenching and conduit, light poles, and EV-charger setting; asphalt striping; and parking-garage concrete, masonry, and fire-protection systems.
  - Abatement and demolition, followed by construction of Buildings 1–4 and a clubhouse supporting up to 90 affordable rental units and 160 parking spaces.
  - Environmental remediation includes excavation and off-site disposal of approximately 9,300 cubic yards of contaminated soil, backfill and a site cover, institutional controls, and ongoing site management and monitoring.
  - Construction management is included for the County-funded infrastructure work.
- **Notable requirements and context**
  - The redevelopment replaces 70 public housing units with up to 90 affordable rental units. Units are intended for households at or below 50% and up to 60% of area median income and must remain affordable for at least 50 years.
  - Electric-vehicle charging stations are required. Parking fees require County approval.
  - Geotechnical recommendations identify soft organic and varved clays near Buildings 3 and 4, with settlement concerns affecting foundation and construction planning.
- **Performance period**
  - The solicitation states a two-year contract term. The attached schedule describes phased construction lasting roughly two to two-and-a-half years, while related County funding and development documents describe additional completion and affordability timelines. No option years are specified.

### Description

The project involves infrastructure improvements associated with the redevelopment of Franklin Courts in Tarrytown. Work includes grading, excavation and soil management; stormwater, sanitary sewer and water main installation; retaining walls; electrical trenching, conduit, light poles and EV charger setting; asphalt striping; and landscaping. The scope also includes parking garage concrete, masonry and fire protection systems. Bids must be submitted physically by December 1, 2026, at 11:00 AM.