# Lee County Ionwave #B260383SML Addendum 5

LeeTran electric bus charger site and infrastructure construction

**Posted:** October 02, 2026
**Respond By:** November 06, 2026
**Identifier:** B260383SML Addendum 5
**NAICS:** 237990, 237310

Lee County is seeking a contractor to build site and infrastructure improvements for two electric bus chargers at LeeTran Headquarters in Fort Myers.
- **Government buyer:** Lee County Board of County Commissioners, through Lee County Procurement Management; project location and transit operator: LeeTran Headquarters, Fort Myers, Florida.
- **Work requested:** One construction project supporting two electric bus chargers, including demolition, excavation and trenching, concrete equipment pads, protective bollards, pavement restoration and markings, erosion and sediment controls, and related site improvements.
- **OEMs and equipment referenced:** **ChargePoint** chargers, including references to Express Plus Power Blocks, Power Link dispensers, Power Link 2000 equipment, and a Variation B pedestal mount; **ABB** XT5H breakers; and a **GE** Spectra switchboard. These references do not establish separate equipment purchases, quantities, or part numbers. The County is identified as owning the chargers; responsibility for furnishing some referenced equipment is not fully resolved in the available material.
- **Notable requirements:** The project is funded in part or whole by the Federal Transit Administration, with applicable federal grant provisions, including Buy America requirements for manufactured products. Bidders are asked to provide one total project price.
- **Performance:** Substantial completion is specified within 30 calendar days after the Notice to Proceed or purchase order. An addendum refers questions about a 45-day schedule to earlier addenda, so no separate definitive duration is established there.

### Description

Lee County Board of County Commissioners seeks a qualified contractor to construct improvements for the LeeTran Electric Bus Charging Infrastructure project at LeeTran Headquarters in Fort Myers, Florida. Work includes site demolition, excavation and trenching, concrete equipment pads, protective bollards, pavement restoration and markings, erosion and sediment controls, and related site improvements supporting electric bus charging infrastructure. The project is funded in part or in whole by the Federal Transit Administration, and vendors must comply with applicable federal grant requirements under 2 CFR Part 200. Sealed bids may be submitted electronically through Ion Wave or delivered by hand before the stated deadline.

[View original listing](https://leegov.ionwave.net/PublicDetail.aspx?bidID=910&SourceType=1)