# Washington Brementon Civic Plus #217

SR 303 vehicle detection and fiber-optic communications installation

**Posted:** October 29, 2026
**Respond By:** November 20, 2026
**Identifier:** 217
**NAICS:** 237310, 237130, 238210

The City of Bremerton is seeking bids to install traffic-signal detection and fiber-optic communications improvements along SR 303.
- **Buyer:** City of Bremerton, Department of Public Works & Utilities, Engineering Division; the notice identifies the City Clerk’s office.
- **Work requested:** Furnish and install vehicle detection systems and ITS improvements, including fiber-optic communications between Sheridan Road and NE Riddell Road and a connection to the City’s existing demarcation point at its Olympus Drive NE facility complex. Related work includes wiring, junction boxes and vaults, signal-cabinet work, and pavement restoration.
- **OEMs and vendors:** No equipment OEMs, manufacturers, or brands are specified. ARC is identified as a provider for previewing and ordering contract documents, not as an equipment supplier.
- **Scope boundary:** The adaptive signal control system itself is being procured under a separate contract. Equipment quantities and part numbers are not provided.
- **Notable requirements:** Complete the work within 50 working days after the Notice to Proceed. The attachment summary identifies FHWA funding and a 7% Federal Small Business Enterprise participation goal; the latest notice description omits those details. Work must follow the contract plans, provisions, and applicable WSDOT specifications. Maintain driveway and bus-stop access, provide accessible pedestrian routes when needed, and maintain existing lane widths or a 10-foot minimum where approved.
- **Estimated value:** $1,275,000–$1,475,000.

### Description

The project involves furnishing and installing traffic signal and ITS improvements for an adaptive signal control system, which will be procured under a separate contract. Work includes new vehicle detection systems and a fiber optic communications system along SR 303 between Sheridan Road and NE Riddell Road, connecting to the existing City of Bremerton demarcation point at a city-owned facility complex on Olympus Drive NE. The work must be completed within 50 working days after the commencement date in the Notice to Proceed. The engineer’s estimated cost range is $1,275,000 to $1,475,000.

[View original listing](https://www.bremertonwa.gov/bids.aspx?bidID=217)