# Georgia Procurement Registry #PE-77182-NONST-2027-000000013

Exit 24 Sanitary Sewer System Extension Construction

**Posted:** October 28, 2026
**Respond By:** December 01, 2026
**Identifier:** PE-77182-NONST-2027-000000013
**NAICS:** 237110

Twiggs County is soliciting construction bids for an extension of the Exit 24 sanitary sewer system in Jeffersonville, Georgia.
- **Government buyer:** Twiggs County Board of Commissioners, Twiggs County, Georgia.
- **Scope:** Construct the sewer extension, including approximately 770 linear feet of 10-inch PVC gravity sewer, 1,748 linear feet of 4-inch force main, a lift station, and associated infrastructure.
- **Requested items:** A 16-inch jack-and-bore steel casing, manholes, valves, fittings, one generator, and erosion-control items. Quantities are not stated for several of these items.
- **Construction work:** Includes clearing and grubbing, possible rock removal, installation of the listed infrastructure, and related appurtenances.
- **OEMs:** No product manufacturers or OEMs are identified. **Carter & Sloope, Inc.** is identified as the issuing office; **QuestCDN** is identified as the bid-document platform. Neither is identified as an OEM or bidder.
- **Notable requirements:** The contractor must hold a valid Georgia utility contractor license, and work must be overseen by a Utility Manager certification holder. The project is subject to applicable federal requirements, including the Build America, Buy America Act.
- **Completion period:** 270 consecutive calendar days; no start date is specified.

### Description

Twiggs County is seeking sealed bids for construction of the Exit 24 - Sanitary Sewer System Extension. Work includes approximately 770 LF of 10-inch PVC gravity sewer, 1,748 LF of 4-inch force main, a lift station, jack-and-bore steel casing, manholes, valves, fittings, a generator, clearing and grubbing, and erosion control. The project is funded in whole or in part by SEID Grant funds and/or the GEFA Georgia Fund Program, with applicable federal requirements including BABAA. One contract will be awarded, and the work must be completed within 270 consecutive calendar days.

[View original listing](https://ssl.doas.state.ga.us/gpr/eventDetails?eSourceNumber=PE-77182-NONST-2027-000000013&sourceSystemType=gpr20)