The City of Greenville is seeking a contractor for its 2027 Street Rehabilitation & Preservation Project, covering asphalt repairs and preservation, accessibility upgrades, and related street improvements.
- **Buyer:** City of Greenville, North Carolina — Engineering and Right of Way Services Department; Pitt County. Project ENG-2027-001.
- **OEMs and named products:** No OEM or manufacturer is identified. **Reclamite** is named as the standard maltene-based asphalt rejuvenator; approved alternate proposals are permitted. No part numbers are listed.
- **Base work:** Mill 52,663 SY of pavement; place 5,806 tons of Type S 9.5B surface asphalt, 103 tons of Type I19.0C intermediate asphalt, and 1,358 tons of Type B 25.0 pavement-repair mix. Apply 76,116 SY of Type II double-application micro-surfacing, 48,313 SY of rejuvenator, and crack-seal 52,107 SY.
- **Other base work:** Utility-box and casting adjustments; curb, gutter, sidewalk, driveway-apron, and ADA ramp work; geotextile and earthwork; pavement markings, traffic control, restoration, and removal of 3 trees. Notable quantities include 14 valve boxes and 25 utility castings/covers to adjust or replace, 44 existing wheelchair ramps to remove, and 46 new ramps across four ramp types.
- **Optional alternates:** Seven mill-and-fill locations—Treybrooke Circle, E. 3rd Street, Wyneston Road, Jamestown Road, Placid Way, Darden Drive, and E. 1st Street—and three micro-surfacing locations—Rockport Drive, Lendire Way, and Adams Boulevard. Associated quantities and location-specific curb/ADA, utility, drainage, earthwork, marking, traffic-control, and restoration work are detailed below.
- **Notable requirements:** Work must meet applicable NCDOT standards and specifications. ADA-related ramp and sidewalk improvements are included. Certain locations have an earlier completion milestone; no calendar dates are included here.
- **Performance:** Base contract time is 120 days. Accepted alternates add 2–7 days each, up to 47 additional days if all are accepted. The agreement also provides for completion and readiness for final payment within 150 days after contract times commence.

### Description

The City of Greenville is soliciting bids for its 2027 Street Rehabilitation & Preservation Project. Work includes milling and resurfacing streets, asphalt repairs, micro-surfacing, rejuvenating and crack sealing pavement, ADA improvements, curb and gutter repairs, and adjustments to valves and manholes. The project also includes pavement markings and tree removal; the base contract time is 120 days. Sealed bids are due November 23, 2026, at 2:00 PM, and electronic bids are not permitted.

[View original listing](https://evp.nc.gov/solicitations//details/?id=4aee28f5-49d2-f111-a05c-001dd803db57)