The City of Covington is seeking a contractor to upgrade overhead electric distribution lines across three projects in Georgia.
- **Buyer:** City of Covington, Georgia, through the Purchasing Department and Covington Power.
- **Work requested:** Reconduct three-phase overhead utility lines at Cornish Creek WTP, Elm Street, and Covington #6. The City supplies materials; the contractor provides labor, equipment, and coordination.
  - **Cornish Creek WTP:** Replace existing conductors with 336 ACSR across spans shown between poles 1 and 15, with associated distribution work.
  - **Elm Street:** Perform the reconductoring and related pole, conductor, and distribution-equipment work shown in the project plans.
  - **Covington #6:** Reconduct 1,870 feet of overhead line between poles E1 and 8, replacing 1/0 ACSR with 336 ACSR, with related distribution work.
- **OEMs and vendors:** No manufacturers, OEMs, or contractor vendors are named in the available notice. The City of Covington is the buyer, not a product vendor.
- **Notable requirements:** Payment and performance bonds are each required at 100% of the contract amount, and a 5% bid bond is required.
- **Schedule:** The work is to be completed by the solicitation’s stated completion deadline. No option years or subscription term are identified.

### Description

The City of Covington, Georgia, is seeking proposals to reconduct three-phase overhead utility lines across three separate projects in Covington. The City will supply the materials, while the selected contractor is responsible for labor, equipment, and coordination; work must be completed by May 31, 2027. Proposals are due November 24, 2026, at 10:00 a.m., and attendance at the November 9, 2026, pre-proposal meeting is mandatory. A 5% bid bond is required, and the awarded contractor must provide payment and performance bonds equal to 100%.