# New York State Contract Reporter #2139395

Hempstead Clinton Street Water Plant AOP Treatment Phase I site work

**Posted:** September 28, 2026
**Respond By:** October 27, 2026
**Identifier:** 2139395
**NAICS:** 237110, 237990

The Incorporated Village of Hempstead is seeking a construction contractor for Phase I site work at the Clinton Street Water Plant AOP Treatment project.
- **Government buyer:** Incorporated Village of Hempstead, Board of Trustees; Office of the Treasurer, Attn: Purchasing Agent Larry Lutz. The work is at the Clinton Street Water Plant in Hempstead, Nassau County, New York.
- **Scope:** Install 6-, 8-, and 10-inch cement-lined ductile-iron water mains; fittings, valves, hydrant, blow-off, and water-main connections; and complete chlorination and trench compaction. Site work also includes a concrete apron and curb cut, 30-inch storm-sewer relocation, stormwater-pollution-prevention work, excavation and disposal, soil placement, recycled-concrete-aggregate restoration, a sliding chain-link gate, and removal of seven trees.
- **Quantities:** Approximately 45 linear feet of 6-inch main, 270 feet of 8-inch main, and 460 feet of 10-inch main; 2,750 pounds of fittings; 2 six-inch, 1 eight-inch, and 2 ten-inch gate valves; 1 hydrant; 2 ten-by-ten-inch water-main cut-ins; and 1 twelve-by-eight-inch wet-cut connection. Chlorination and trench compaction are each listed at 775; SWPPP maintenance is estimated at 30 months.
- **Named OEMs and products:** **Mueller** Super Centurion A421 hydrant, with a 4-inch valve and NYC threads on both hose connections. The gate details specify a **TYMETAL** TYM-SL-2000DC gate/operator system with a 30-foot clear opening. Clow Eddy is referenced in the original hydrant specification, but the addendum clarifies that Mueller is required.
- **Notable requirements and clarifications:** The contract has a 26% combined MWBE participation goal and applicable prevailing-wage, DBE, Build America, Buy America, and American Iron and Steel requirements. Work is due within 210 consecutive calendar days after notice to proceed; listed work milestones range from 90 to 180 days, while SWPPP maintenance is estimated at 30 months. Asphalt restoration is limited to the Clinton Street curb cut; on-site asphalt restoration and several other site features, including sidewalks, curbs, containment slabs, AST and blower-pad foundations, and bollards, are excluded. Silt fencing is not required around the construction entrance or along its street-facing side.
- **Estimated value:** $602,444.

### Description

The Village of Hempstead is seeking bids for Phase 1 site work at the Clinton Street Water Plant as part of the Clinton Street Water AOP Treatment project, Contract No. 1-6.1. The scope includes water main installation and relocation, valves and hydrants, chlorination, a concrete apron and curb cut, storm sewer relocation, stormwater pollution prevention, excavation and site restoration, and a sliding chain-link gate. The contract estimate is $602,444.00, and the bid documents state that all work must be completed within 210 consecutive calendar days after the notice to proceed. Addendum No. 1 states that the successful bidder must implement a Minority & Women Owned Business Enterprise utilization plan with a combined goal of 26%.

[View original listing](https://www.nyscr.ny.gov/Ads/Search)