# SAM #1240LT27Q0012

Remove two underground fuel tanks and restore the Nelson Drive housing site

**Buyer:** USFS CSA Intermountain Region 8
**Posted:** October 23, 2026
**Respond By:** November 14, 2026
**Identifier:** 1240LT27Q0012
**NAICS:** 237120, 562910

The USDA Forest Service is seeking a contractor to remove underground heating-oil tanks and restore the site at the Nelson Drive housing complex on the Bridger-Teton National Forest.
- **Government buyer:** U.S. Department of Agriculture (USDA), Forest Service; identified offices include CSA Intermountain 8, Region 4, and the Bridger-Teton National Forest’s Jackson Ranger District.
- **Scope:** Remove and dispose of two approximately 300-gallon underground steel heating-oil tanks, associated piping, and appurtenances at 350 and 360 Nelson Drive in Jackson, Wyoming. Work includes soil sampling, excavation, backfill, and restoration of the site.
- **Additional work:** Mobilization; selective removal of concrete and grassed areas as needed; and concrete sidewalk restoration. The attachments differ on sidewalk quantities: one schedule lists 500 square feet of 4-inch concrete removal, while another describes approximately 300 square feet of replacement at an additional dwelling.
- **Optional work:** Remove and dispose of contaminated soil at an authorized facility, with a maximum quantity of 20 cubic yards. Soil testing and cleanup/disposal are also included in the base-work descriptions where contamination is found.
- **Requirements:** Tank decommissioning must meet Wyoming Department of Environmental Quality (WYDEQ) requirements. Contractors must protect occupied residences, adjacent structures, and utilities; field-verify site conditions; and restore disturbed areas.
- **Named OEMs and commercial vendors:** No product manufacturers, OEMs, or commercial vendors are identified. WYDEQ is named as a regulatory agency, not a vendor.
- **Performance:** Contract work is scheduled for 30 calendar days, with tank and contaminated-soil removal specified for completion within 21 calendar days.

### Description

<p>This project includes the removal of two existing steel underground fuel storage tanks at<br />
the Nelson Drive housing complex on the Bridger-Teton National Forest; two 300-gallon<br />
steel underground fuel storage tanks associated with two neighboring residential<br />
dwellings. This includes cleanup and disposal of any contaminated soils. Contractor shall<br />
field verify all new and existing conditions affecting the work of this contract before<br />
ordering products.</p>