# PIEE #W912CN026793

Sources Sought for LAN/DLAN Engineering and Installation Support for NIPR/SIPR Networks

**Buyer:** 0413 AQ HQ     RCO-HI
**Posted:** October 22, 2026
**Respond By:** October 30, 2026
**Identifier:** W912CN026793
**NAICS:** 541519, 541330, 238210, 237130

The U.S. Army is seeking industry capability information for network engineering and installation support across Pacific Region installations.
- **Government buyer:** U.S. Army; contracting office: KO Directorate of Contracting, Fort Shafter, Hawaii; customer office listed as 0413 AQ HQ RCO-HI; supported organization: Network Enterprise Center (NEC).
- **Work requested:** LAN/DLAN and NIPRNET/SIPRNET site surveys, requirements analysis, secure network architecture design, cable-plant installation, telecom-room remediation, and fiber- and copper-cabling installation and repair.
- **Deliverables:** Engineering Installation Plans (EIPs), a Bill of Materials (BOM), updated network topology diagrams, and draft System Security Plans (SSPs). Work must comply with DISA STIGs and DoD enterprise standards.
- **Notable requirements:** Government reviews and approval are required at the Initial and Final Design Reviews. Physical installation or network integration requires a Government Authority to Proceed.
- **Set-aside and vendor information:** Total small-business set-aside. No OEMs, vendors, products, part numbers, or quantities are identified. The notice seeks capability information; proposals are expected under a later solicitation.

### Description

NIPR / SIPR drops Blanket Purchase Agreement - LOCAL AREA NETWORK (LAN)/DEPLOYABLE LOCAL AREA NETWORK (DLAN) ENGINEERING AND INSTALLATION SUPPORT TO NETWORK ENTERPRISE CENTER (NEC)The contractor shall provide personnel, management, and any other items and services engineering design, cable plant installation, telecom room remediation, fiber/copper installation and repair, SIPRNET/NIPRNET cabling to perform installation of task. The NIPR and SIPR network planning and engineering process encompasses comprehensive site surveys, requirements analysis, and secure architecture design to ensure strict compliance with DISA STIGs and DoD enterprise standards. The expected outputs of this phase include detailed Engineering Installation Plans (EIPs), complete Bill of Materials (BOM), updated Network Topology Diagrams, and draft System Security Plans (SSPs). To ensure mission alignment and security compliance, formal Government review and approval will occur at critical milestones¿¿¿¿¿¿¿¿¿¿¿¿¿¿¿¿¿¿¿¿¿¿¿¿¿¿¿specifically during the Initial Design Review (IDR) and Final Design Review (FDR)¿¿¿¿¿¿¿¿¿¿¿¿¿¿¿¿¿¿¿¿¿¿¿¿¿¿¿culminating in a formal Authority to Proceed (ATP) before any physical installation or network integration activities commence. This is a Sources Sought notice interested parties should provide a capabilities statement along with CAGE code and Small Business status. Notice for proposals for the Blanket Purchase Agreement will be posted later.

[View original listing](https://piee.eb.mil/sol/xhtml/unauth/search/oppMgmtLink.xhtml?noticeId=W912CN026793&noticeType=SourcesSought)