# City of Lincoln Ionwave #26-204

Lancaster County Solicits Chip Sealing for Eight County Road Segments

**Posted:** October 21, 2026
**Respond By:** November 04, 2026
**Identifier:** 26-204
**NAICS:** 237310

Lancaster County Engineering is seeking a contractor for chip sealing on eight county road segments.
- **Government buyer:** Lancaster County Engineering Department, Lancaster County; the County Engineer’s office, with Lincoln Purchasing identified in the bid materials.
- **Work requested:** Eight separately priced chip-sealing sections, each with a lump-sum bid and supporting itemized spreadsheet:
  - Adams Street, Stevens Creek to N. 148th Street
  - Holdrege Street, city limits to N. 148th Street
  - NW 112th Street, Malcolm Road to Alvo Road
  - W. Fletcher Avenue, NW 48th Street to one mile west
  - W. Rokeby Road, SW 12th Street to 0.61 miles east
  - W. Sprague Road, SW 14th Street to Highway 77
  - Firth Road, S. 68th Street to the Firth city limits
  - SW 29th Street, Highway 33 to Kildeer Lake
- **Schedule and scope requirements:** Provide a proposed work sequence and project schedule for the eight locations. The project is specified as 92 calendar days; no part numbers or construction-product quantities are provided.
- **OEMs:** No original equipment manufacturers or specified construction-product brands are identified.
- **Other named suppliers and plan holders:** Invited suppliers listed are 360 Clean, LLC; 4 Ways Delivery LLC; 4G Steel Fabrication; 4LEAF, Inc; 4X Construction Group, LLC; A&H CO, INC.; A.M. Cohron & Son Inc.; A.M.B HANDYMAN SERVICE LLC; A.T.G.-Ram Industries,LLC; A-1 Pump & Jet Services Inc; A1A Sandblasting (Iowa); A2Z Provision LLC; A6 Scientific Corp.; ABC Abatement Company; and ABJ HAULING LLC. Plan holders listed are Lincoln Builders Bureau; Master Builders of Iowa; National Concrete Cutting, Inc.; North Orchard; and Transduction Technologies.

### Description

Lancaster County is seeking bids for chip sealing work under the 2026 project, divided into eight parts covering Adams Street, Holdrege Street, NW 112th Street, W. Fletcher Avenue, W. Rokeby Road, W. Sprague Road, Firth Road, and SW 29th Street. Bidders must submit lump-sum bids and completed itemized spreadsheets for the parts, along with a project schedule and the required certification form. Work is to begin on or after June 1, 2027, and be completed by August 31, 2027, within a 92-calendar-day project period. A bid bond or certified check equal to 5% of the total bid is required.

[View original listing](https://col.ionwave.net/PublicDetail.aspx?bidID=17745&SourceType=1)