# New York State Contract Reporter #2140031

PE-Stamped Design for Generac Standby Generator Replacement at Wedgewood IRA

**Posted:** October 19, 2026
**Respond By:** November 12, 2026
**Identifier:** 2140031
**NAICS:** 541330, 541310

OPWDD is seeking professional engineering design for a standby generator replacement at Wedgewood IRA in Middletown, New York.
- **Government buyer:** New York State Office for People With Developmental Disabilities (OPWDD), Hudson Valley DDSO Business Office.
- **OEM:** **Generac** is specified for the standby generator; the design must also include an automatic transfer switch. No specific model or part number is provided.
- **Requested service:** One design project to replace the existing diesel generator with a natural-gas- or propane-fueled whole-house standby system. The work includes reviewing the existing pad and electrical service, surveying the site, analyzing whole-house electrical loads, and sizing the system.
- **Design requirements:** Provide electrical, gas-piping, and conduit plans; a one-line electrical diagram; and an installation cost estimate. Address a cold-weather start kit, block and battery heaters, a generator service outlet, an accessible exterior disconnect, and underground line tracer and burial tape.
- **Deliverables and schedule:** Submit PE-stamped drawings in PDF and CAD (.dwg) formats for OPWDD engineer acceptance. Complete the work within 30 days of receiving the purchase order.
- **Other named vendors or OEMs:** None besides Generac are identified in the supplied materials.

### Description

This is a request for quotation for design-only services for a standby whole-house generator at Wedgewood IRA in Middletown, New York, replacing an existing diesel generator with a natural gas- or propane-fueled generator. The work includes providing PE-stamped design drawings in PDF and CAD formats, assessing the existing site and electrical services, specifying a generator and automatic transfer switch, and preparing a cost estimate for installation. The design must meet the stated code requirements and be accepted by the OPWDD engineer; the design work is to be completed within 30 days of receiving the purchase order. A mandatory site visit is required, and quotes are due November 12, 2026 at 2:00 PM.