# Owasso Civicplus #294

Bailey Ranch Golf Club Hole 16 Bridge Replacement and Approach Restoration

**Posted:** October 13, 2026
**Respond By:** November 17, 2026
**Identifier:** 294
**NAICS:** 237310, 237990

The Owasso Public Golf Authority is seeking construction bids to replace the Bailey Ranch Golf Club Hole 16 bridge and restore its approaches.
- **Government buyer:** Owasso Public Golf Authority, under the City of Owasso, Oklahoma; project coordination involves the City’s Public Works Department, Engineering Division. Named contacts in the documents include Civil Engineer Daniel Dearing and Corey Burd.
- **Bridge and OEMs:** Furnish and install one 60-foot-by-12-foot pedestrian truss bridge, described as a half-through H-section with parallel chords and Pratt diagonals. **No bridge OEM, manufacturer, or model part number is specified.** The bridge supplier must provide final stamped and sealed structural design details and reinforcement schedules.
- **Construction items:** 25 cubic yards of ODOT Class A, 3,000-psi concrete for abutments; 1,220 pounds of reinforcing steel; and 62 square yards of 6-inch-thick concrete cart path with curb, using ODOT Class AA, 4,000-psi concrete and Type A aggregate base.
- **Other work and materials:** Remove and relocate the existing bridge to the City storage yard; demolish and dispose of existing concrete; install and remove a temporary 12-inch-thick mulch access road over filter fabric; and complete site restoration. Restoration includes Astro Bermuda sod (regular Bermuda is permitted with City approval), riprap and filter blanket at the abutments, grading, landscaping, and cart-path repairs. Plans show approximately 40 square yards of riprap; it is included in site restoration rather than separately paid.
- **Geotechnical information:** Terracon prepared the project geotechnical reports and recommendations; it is not identified as a bridge supplier or bidder. The addendum recommends at least 24 inches of compacted ODOT Type A aggregate base beneath shallow footings, with a maximum net allowable bearing pressure of 2,000 psf, and geotechnical observation of footing excavations. The report also specifies minimum footing dimensions and depth.
- **Schedule:** Construction is to reach substantial completion within 60 calendar days after Notice to Proceed and final completion within 90 calendar days. A two-year maintenance bond applies after project acceptance. No specific contract start date is stated.

### Description

The solicitation is for renovation of a golf cart bridge at Bailey Ranch Golf Club, including removal and replacement of the existing bridge and a portion of the approaches on either side. The project documents describe installation of a new 60-foot by 12-foot bridge, bridge abutments, concrete cart path, and site restoration. Bids are due November 17, 2026, at 2:30 PM, and a representative must attend the mandatory pre-bid meeting on November 10, 2026, at 2:30 PM for the bid to be considered. Sealed bids are to be delivered to Public Works in Owasso, Oklahoma.

[View original listing](https://www.cityofowasso.com/bids.aspx?bidID=294)