Kilauea Point Roadway, Pedestrian, and Bicycle Access Improvements

**Buyer:** Central Federal Lands Highway Division
**Posted:** October 15, 2026
**Identifier:** 6982AF27B000008
**NAICS:** 237310

The Federal Highway Administration is planning road, pedestrian, and bicycle access improvements near Kilauea Point National Wildlife Refuge on Kauaʻi.
- **Government buyer and partners:** Federal Highway Administration (FHWA), Central Federal Lands Highway Division, coordinating with Kilauea Point National Wildlife Refuge and the U.S. Fish and Wildlife Service.
- **Project location and scope:** Approximately 1.70 miles along Kolo Road and Kilauea Road (Route 562), from Kuhio Highway to the refuge overlook. Work includes roadway rehabilitation and resurfacing, widening, turnaround reconstruction, two mini-roundabouts, pedestrian crossings, striping, guardrail, sidewalks, curbs, and minor utility work.
- **Major quantities:** 18,500 square yards of asphalt pavement removal; 3,370 cubic yards of roadway excavation; 2,900 tons of roadway aggregate; 4,200 tons of Type 1 asphalt concrete pavement; 630 square yards of reinforced minor concrete pavement; 1,540 linear feet of slotted concrete curb; 5,670 square yards of concrete sidewalk; and 34 concrete accessibility ramps.
- **OEMs and vendors:** No OEMs, manufacturers, or vendors are identified.
- **Estimated project value:** $10 million to $20 million.
- **Notice status:** This is an advance notice for a planned construction project; plans and specifications are not provided.

### Description

<p><strong>THIS IS NOT AN INVITIATION FOR BID, PLAN AND SPEFICIATIONS ARE NOT AVAILBLE</strong></p>

<p></p>

<p><strong>PROJECT NAME:&nbsp;</strong>HI FLAP CR562(1) Kilauea Point</p>

<p><strong>PROJECT DESCRIPTION:</strong></p>

<p>Kilauea Point National Wildlife Refuge (KPNWR) is a 203-acre facility located on the north shore of the Island of Kaua&#39;i. It is part of the Kaua&#39;i National Wildlife Refuge Complex managed by the United States Fish and Wildlife Service. To keep up with the visitation demands, the KPNWR and the USFWS along with the Federal Highway Administration Central Federal Lands Highway Division is proposing to improve the area by providing better access along Kolo Road and Kilauea Road (Route 562) for pedestrians and bicyclists, as well as improvements to the overlook.</p>

<p>The project consists of installation of a sidewalk adjacent the existing roadway from the intersection of Kuhio Highway to the KPNWR Overlook. Work includes pavement rehabilitation and resurfacing of the existing roadway, with full depth pavement on aggregate base course for roadway widening segments, and reconstruction of the existing turnaround. Guardrail, sidewalk, curb, gutter, two mini-roundabouts, striping, and pedestrian crossings will be provided to establish a safe and accessible corridor for pedestrians and bicyclists. Minor utility adjustments and construction is also anticipated. The total project length is approximately 1.70 miles.</p>

<p><strong>PRINCIPAL WORK ITEMS:</strong></p>

<ul>
	<li>18,500 square yards of Removal of Pavement, Asphalt</li>
	<li>3,370 cubic yards of Roadway Excavation</li>
	<li>2,900 ton of Roadway Aggregate, Method 2</li>
	<li>4,200 ton of Asphalt Concrete pavement, Type 1</li>
	<li>630 square yard of minor concrete Pavement, Reinforced</li>
	<li>1,540 linear feet of Curb, Concrete, 16-Inch Depth (Slotted)</li>
	<li>5,670 square yards of Sidewalk, Concrete</li>
	<li>34 Accessibility Ramps, Concrete</li>
	<li></li>
</ul>

<p><strong>ANTICIPATED SCHEDULE:&nbsp;</strong></p>

<p>Advertise: End of October or Early November 2026</p>

<p>Bid Opening: December 2026</p>

<p>Award: January 2027</p>

<p>Construction:&nbsp; January 2027 &ndash;January 2028</p>

<p></p>

<p><strong>ESTIMATED COST RANGE:</strong> The anticipated cost range is between 10,000,000 and $20,000,000.</p>