# Utah Public Procurement Place U3P #EMC-FY27-08

Final Engineering Design for Eagle Mountain City Sewer Trunkline and Reuse Pipeline

**Posted:** October 14, 2026
**Respond By:** November 04, 2026
**Identifier:** EMC-FY27-08
**NAICS:** 541330

Eagle Mountain City is seeking an engineering consultant to complete final design for its East Trunkline sewer and parallel Tickville reuse-discharge pipeline.
- **Government buyer:** Eagle Mountain City, Engineering Department; Melissa Yates, Purchasing Agent.
- **Requested services:** Advance the existing 30% design to 100%, including hydraulic and system analysis, alignment and pipeline/appurtenance design, utility-conflict review, geotechnical and subsurface assessment, property and easement impacts, environmental and permitting review, and construction phasing and maintenance-of-service considerations.
  - Geotechnical work includes up to 20 borings: 18 shallow borings to 15 feet and 2 deep borings to 29 feet.
  - The East Trunkline design includes upsizing an existing 24-inch pipe to 30 inches. The parallel reuse pipeline extends to Tickville Gulch; its required pump station is outside the referenced preliminary design.
- **Deliverables:** Final design drawings, specifications and bid documents in PDF and editable formats; a comprehensive engineering report; and an itemized, bidding-level construction cost estimate with supporting basis-of-estimate documentation. The consultant will also support budgeting, Capital Improvement Plan programming, right-of-way planning, and bidding.
- **Prior work and vendor:** Eagle Mountain City commissioned **JWO Engineering** to prepare the existing 30% design. No new OEMs or product vendors are identified; this is a professional engineering-services procurement.
- **Preliminary construction-cost context:** The prior design report estimated $21.5 million for the trunkline and an additional $13.8 million for the reuse pipeline. These are construction estimates, not the value of this design-services contract.
- **Performance period:** Complete the work within 180 days after contract execution. No option periods or annual subscription are specified.

### Description

Eagle Mountain City is requesting proposals to advance the existing 30% design of a sewer trunkline and parallel effluent disposal line to 100% design. Services include project management, hydraulic evaluation, alignment and pipeline design, utility-conflict analysis, and preparation of final design drawings, specifications, bid documents, an engineering report, and a construction cost estimate. The consultant must complete the work within 180 days of contract execution. Proposals are due November 4, 2026, at 12:00 PM MST.

[View original listing](https://utah.bonfirehub.com/opportunities/258557)