The City of Maryville, Missouri, is seeking a contractor for the South Main Trail Connection Project.
- **Government buyer:** City of Maryville, Missouri; City Clerk.
- **Project:** TAP-4301107, approximately 570 linear feet of new 10-foot-wide concrete trail connecting the existing trail north of Mosaic Medical Center to the existing sidewalk at South Main Street.
- **OEMs and vendors:** No product OEMs are identified. Drexel Technologies is named as the plan-room and contract-document provider, not as the project contractor or an OEM.
- **Key requirements:** Contractor must be MoDOT-qualified; prevailing-wage requirements apply; the DBE goal is 0%; second-tier subcontracting is not allowed; and on-site employees must complete an approved 10-hour construction safety program within 60 days of starting work. Bid security is 5%.
- **Performance:** Work must be completed within 90 calendar days; the completion date is to be determined. Liquidated damages are $700 per day for late completion.

### Description

The City of Maryville is seeking bids to construct approximately 570 linear feet of new 10-foot-wide concrete trail. The trail will connect the existing trail on the north side of Mosaic Medical Center at the west end to the existing sidewalk at South Main Street at the east end. Bids are due November 10, 2026, at 2:00 PM prevailing local time, and a pre-bid conference is scheduled for October 28, 2026, at 2:00 PM. Bid security is required in accordance with the Instructions to Bidders.