# Hawaii eProcurement Portal #B27000533

Pier 51A domestic and fire waterline replacement construction

**Posted:** October 08, 2026
**Respond By:** December 03, 2026
**Identifier:** B27000533
**NAICS:** 237110, 237990

Hawaii DOT Harbors is seeking a contractor to replace domestic and fire waterlines at Pier 51A in Honolulu Harbor.
- **Government buyer:** State of Hawaii Department of Transportation, Harbors Division, Air and Water Transportation Facilities Division; project location is Pier 51A, Honolulu Harbor, Oahu. Job P10904.
- **Scope:** Remove existing waterlines and install new domestic-water and fire-protection lines, hydrants, valves, appurtenances, and related connections. Restore pavement and trenches, provide traffic controls, and complete environmental controls and testing.
- **Pipe quantities:** 280 linear feet of 6-inch pipe, 1,950 linear feet of 8-inch pipe, and 600 linear feet of 12-inch pipe are in the base bid. An additive alternate includes 320 linear feet of 1½-inch pipe. The specifications call for Class 53 ductile iron pipe with bonded dielectric coating for the 6-, 8-, and 12-inch lines.
- **Other work:** Includes demolition, asphalt pavement and base-course work, signage and pavement markings, and management of potentially contaminated soils, contaminated sediment, oily groundwater product, and an existing asbestos-containing waterline. Environmental planning documents, including a Construction Environmental Hazard Management Plan, and qualified environmental consultant services are required.
- **Notable requirements:** Contractor must hold a valid Hawaii General Engineering “A” license. At least 80% of the bidder’s project workforce must consist of Hawaii residents; an apprenticeship agreement may qualify the bidder for a 5% bid adjustment.
- **Estimated construction cost:** $10 million to $13 million. Performance is 450 calendar days from the Notice to Proceed; no option years or annual subscription are stated.
- **OEMs and vendors:** No product manufacturers, OEMs, or commercial vendors are named.

### Description

The project replaces the existing fire protection and domestic water system within Pier 51A at Honolulu Harbor, including trench restoration and temporary phasing. The estimated construction cost is between $10,000,000 and $13,000,000. Bidders must hold a valid State of Hawaii General Engineering “A” license at the time of bidding. Bids must be submitted through HIePRO by December 3, 2026, at 2:00 p.m. HST.

[View original listing](https://hiepro.ehawaii.gov/public-display-solicitation.html?rfid=27000533&resetCookie)