The City of Carrollton is seeking a contractor to renovate the Crosby Recreation Center while keeping the facility operational.
- **Buyer:** City of Carrollton, Texas; no specific department or office is identified.
- **Work requested:** Renovate the reception area; perform selective demolition; replace ceiling grid, ceiling tile, and interior lighting; paint interior and office areas; and modify electrical systems and HVAC ductwork to support the renovations.
- **Operations and coordination:** Protect and temporarily relocate furniture, equipment, fixtures, files, and other items as needed. The contractor must coordinate construction phasing and scheduling with City staff and vendors while the center remains open. Work is generally expected during normal working hours.
- **Furniture and infrastructure:** The City will purchase and install furniture; the contractor provides the required electrical and low-voltage infrastructure.
- **OEMs and named vendors:** **Crestron Controls and Sensors** is referenced in the drawings in connection with lighting controls, but the system identification is subject to clarification. IonWave Technologies, Inc. is identified as the bidding-system provider, not as a construction supplier.
- **Estimate:** The engineering estimate is $1,500,000.
- **Products and quantities:** No standalone products, part numbers, or quantities are specified.

### Description

The City of Carrollton is seeking bids for renovations at the Crosby Recreation Center. Work includes reception-area adjustments, selective demolition, ceiling grid and tile replacement, interior lighting, painting, electrical modifications, and HVAC ductwork adjustments. The contractor must protect and temporarily relocate furnishings and equipment as needed and develop a construction phasing plan coordinated with city staff and vendors while maintaining center operations. The engineering estimate is $1,500,000; the recreation center will remain open during construction, with work expected during normal working hours.