# Coachella Valley Water District PlanetBids #2024-13

East Side Dike Realignment and Rehabilitation Construction

**Posted:** October 06, 2026
**Respond By:** November 10, 2026
**Identifier:** 2024-13
**NAICS:** 237990

Coachella Valley Water District is seeking a contractor to realign and rehabilitate the East Side Dike between Wasteway No. 3 and Dillon Road in Riverside County.
- **Government buyer:** Coachella Valley Water District (CVWD), Engineering Department.
- **Procurement:** Construction of approximately 3,400 linear feet of realigned dike, access routes, a turnaround, and related earthwork and protections.
- **Main quantities:** 440 LF of access ramp; 3,650 LF of 20-foot-wide upper access road; 3,570 LF of 15-foot-wide lower access road; approximately 18,000 SF of 2-inch Class 2 aggregate base; and a 2,250 SF turnaround. Plans also call for construction of the realigned dike and one pipe gate. Large debris removal is listed at 100, with the unit not specified in the available summary.
- **Other bid items:** Mobilization and demobilization; dust control and a PM10 plan; a stormwater pollution prevention plan; surveying; temporary flood protection; ground-vibration monitoring and control; earthwork; all-risk installation floater insurance; and allowances of $500 for an encroachment permit and $100,000 for unidentified construction items or utilities.
- **Notable requirements:** Class A General Engineering License, mandatory pre-bid site meeting, at least 30% contractor self-performance, CARB fleet compliance, continuous vibration monitoring during earthwork, and flood and earthquake coverage under the installation floater. Liquidated damages are $4,000 per day. The work must be completed within 120 working days from the Notice to Proceed.
- **Relevant technical context:** CVWD-commissioned geotechnical reports by GENTERRA Consultants, Inc., including work requested by Northwest Hydraulic Consultants, discuss levee certification and dike improvement recommendations. Separate recommendations cover erosion and scour protection and crest grading; these broader mitigation recommendations are not presented as priced line items in this construction bid.
- **OEMs:** No product manufacturers or OEMs are identified. This is principally a civil construction procurement.
- **Named prospective bidders and other vendors:** 395 Structures, LLC; Bosco Constructors, Inc.; Clean Harbors Environmental; Contera Construction Company; Elite Earthworks & Engineering; GSA Contract Services, LLC; Harris & Associates, Inc.; HELIX Environmental Planning, Inc.; Hi-Grade Materials Co; Jeremy Harris Construction, Inc.; Larison Contracting Corp.; MDB General Engineering, Inc.; Ortiz & Son Inc; Petra Geosciences, Inc; Proactive Engineering Consultants; Sukut Construction, LLC; Terracon Consultants, Inc.; Twining, Inc.; URSteel LLC; GENTERRA Consultants, Inc.; and Northwest Hydraulic Consultants. Prospective bidder listings do not indicate contract award.

### Description

Coachella Valley Water District seeks bids for realignment and rehabilitation of approximately 3,400 linear feet of the existing East Side Dike between Wasteway No. 3 and Dillon Road. The work includes construction of the realigned dike, access roads and ramp, Class 2 aggregate base, and related earthwork and project requirements. Bids are submitted electronically through PlanetBids, and a hard-copy bid bond must also be delivered to the District before the deadline. The solicitation requires a Class A General Engineering License and identifies the pre-bid meeting as mandatory.

[View original listing](https://vendors.planetbids.com/portal/16339/bo/bo-detail/146987)