# City of Sacramento PlanetBids #B27151111003

Sacramento R Street pedestrian, roadway, traffic-signal, and rail-crossing improvements

**Posted:** September 30, 2026
**Respond By:** October 28, 2026
**Identifier:** B27151111003
**NAICS:** 237310, 237990

The City of Sacramento is seeking a contractor for federally funded pedestrian, roadway, traffic-signal, drainage, and rail-crossing improvements along R Street and nearby streets.
- **Buyer:** City of Sacramento, Department of Public Works, Engineering Services.
- **Scope:** Work along R Street between 28th Street and Alhambra Boulevard, and 29th and 30th Streets between Q Street and S Street. The project includes accessible pedestrian facilities, roadway and pavement rehabilitation, drainage and utility work, signs and markings, new traffic signals, fiber-optic interconnection, and rail-crossing equipment work.
- **Named OEMs:** **McCain** (ATC Flex 1 controllers and Fourth Dimension D4 software), **Cisco** (IE-3100 switches), **Econolite** (OptiVu video detection), and **Axis** (Quad Panoramic CCTV cameras). No other named product vendors or required OEMs are identified.
- **Notable signal equipment:** Two complete signal installations, at R Street/29th Street and R Street/30th Street, each including a Model 342LX cabinet, McCain controller and software, Cisco switch, Econolite detection, GPS emergency vehicle detection, Axis CCTV, and associated infrastructure.
- **Rail and fiber work:** Install, modify, relocate, test, and commission rail-crossing warning equipment, including gates, flashers, relays, and wiring; furnish and install fiber-optic interconnection and related equipment.
- **Key requirements:** Buy America compliance; coordination and safety controls with SacRT; three trainees; applicable DBE, reporting, nondiscrimination, prompt-payment, and subcontracting requirements, with no DBE contract goal established. Davis-Bacon or California prevailing wage rates apply, whichever is higher.
- **Estimated project value:** $4.8 million. Construction duration is 120 working days, with operational completion due within 105 working days and final completion within 120 working days after field work begins.
- **The bid schedule also includes** roadway excavation and paving, storm-drain work, concrete and curb ramps, detectable warning surfaces, sign work, pavement markings, traffic control, site management, stormwater compliance, potholing, clearing and grubbing, and mobilization.

### Description

The City of Sacramento is seeking bids for pedestrian crossing, traffic signal, accessibility, drainage, utility, and pavement improvements in the R Street and 29th/30th Streets project area. Work includes signalizing the 29th and 30th Street intersections, installing pedestrian facilities, connecting to existing railroad crossing equipment, replacing rail gate and signal equipment, and roadway rehabilitation, signing, and striping. The work is within existing City right-of-way, with construction scheduled for 120 working days. The stated estimated value is $4,800,000.

[View original listing](https://vendors.planetbids.com/portal/15300/bo/bo-detail/146766)