# Coronado Planet bids #27-CO-EN-1204

First Street Stormwater Pump Station Flood Relief Project – Sole-Sourced Equipment and Construction Services

**Posted:** September 23, 2026
**Respond By:** November 09, 2026
**Identifier:** 27-CO-EN-1204
**NAICS:** 237110, 237990

The City of Coronado is seeking bids for the First Street Stormwater Pump Station Flood Relief Project, managed by the Public Services & Engineering Department.
- Government Buyer:
  - City of Coronado, Public Services & Engineering Department, City Engineer's Office
- OEMs and Vendors:
  - Flygt (Xylem Inc.): Pre-Engineered Fiberglass Pump Station, Submersible Pumps
  - Val-Matic Valve & Manufacturing Corp.: Check Valves, Plug Valves
  - FleetZoom: Model FZ400 Monitoring Equipment
  - Tideflex Technologies: Inline Elastomeric Check Valves
  - USF Fabrication: Floor Hatches
- Products Requested:
  - Flygt Pre-Engineered Fiberglass Pump Station (owner furnished), 6' diameter x 11' depth, with two Flygt Model NP-3127.070 submersible pumps (10 HP, 208V, 3-phase)
  - Val-Matic Check Valves (sole-sourced, contractor procured)
  - FleetZoom Model FZ400 Monitoring Equipment (sole-sourced, contractor procured)
  - Pre-cast concrete valve vault with valves, piping, fittings, hatch cover, and appurtenances
  - Ten-Inch C900 PVC DR25 Pipe (approx. 348 LF)
  - Thirty-Inch C900 PVC DR25 Pipe (approx. 10 LF)
  - Plug Valves (Val-Matic)
  - Inline Elastomeric Check Valves (Tideflex)
  - Floor Hatches (USF Fabrication)
  - General electrical system components (metering, grounding, raceways, conductors, overcurrent protection)
- Services Requested:
  - Demolition of existing diverter pump and storm drain diversion structure
  - Installation of new electrical service (including SDG&E service)
  - Traffic control, BMP construction plan preparation, excavation safety measures
  - AC pavement and sidewalk removal/replacement, landscaping restoration
  - Installation of new force main outfall, sump modifications, and connection to existing diversion structure
  - Start-up and testing of installed systems
- Unique/Notable Requirements:
  - Several materials are sole-sourced: Val-Matic Check Valves, FleetZoom FZ400, Flygt Pump Station
  - Compliance with California prevailing wage laws and registration with Department of Industrial Relations
  - California Class A General Engineering Contractor's License required
  - Liquidated damages of $2,000 per day for late completion
  - Environmental compliance and stormwater BMPs required
  - Project location: 101 B Ave, Coronado, San Diego County, CA

### Description

This project involves the removal of the existing diverter pump, partial demolition of the existing storm drain diversion structure, and installation of a pre-engineered fiberglass pump station (owner furnished), pre-cast valve vault with valves, piping, and related appurtenances. Additional work includes modifications and structural improvements to the existing storm drain diverter structure and installation of a new force main outfall and check valves. The project is located at 101 B Ave, Coronado, CA 92118 and is currently in the bidding stage with electronic bid submission. A mandatory pre-bid meeting is scheduled for October 7, 2026, at 10:00 AM. Liquidated damages are set at $2,000 per day, and the estimated contract value is approximately $1,213,400.