# Lincoln Electric System Procureware #124-26

LES seeks Carrier/Bryant certified HVAC installer for heat pump replacement at four substations

**Posted:** September 21, 2026
**Respond By:** October 08, 2026
**Identifier:** 124-26
**NAICS:** 238220

Lincoln Electric System (LES) is seeking bids for the removal and replacement of heat pump systems at four substations in Lincoln, Nebraska.
- Government Buyer:
  - Lincoln Electric System (LES), municipal utility
- OEMs and Vendors:
  - Carrier
  - Bryant
- Products Requested:
  - Heat pump condensing units (Carrier 27SCA524A003, 27SCA548A003; Bryant 235SAN02400A, 235SAN04800A)
  - Fan coil units (Carrier FJ5ANXB36L00, FJ5ANXD60L00; Bryant FJ5ANXB36L00, FJ5ANXD60L00)
  - Electric heat packages (10KW and 15KW)
  - Single point wiring kit accessory (KFASP0101SPK)
  - Electrical disconnects with integrated 120-volt GFCI outlets, ductwork, line sets, and breakers
- Services Requested:
  - Removal of existing heat pump systems (including indoor fan coil units, outdoor condensing units, ductwork, and wiring)
  - Installation of new split system heat pumps and associated components
  - Proper disposal of old units and materials, including refrigerant reclamation
  - Permitting, inspections, and compliance with LES specifications and drawings
- Unique/Notable Requirements:
  - Installer must be Carrier/Bryant certified
  - Minimum 1-year parts and labor warranty; 5-year warranty on condenser compressors
  - Proof of insurance from a Nebraska-licensed, B+ rated insurer
  - Completion of LES Equal Employment Opportunity Compliance Form 51
  - Pre-bid site visit required
  - All work must be completed by the specified completion date

### Description

Lincoln Electric System is requesting bids for an HVAC installer to remove and install 4 heat pump systems per LES specifications included in this bid solicitation. The work involves removal and replacement of heat pumps at four substations located in Lincoln, Nebraska. The successful bidder must complete the LES Standard Contract, provide proof of insurance, and comply with equal employment opportunity requirements. The project requires installation of split system heat pumps, disposal of old units, and adherence to all applicable laws and regulations. All work must be completed by November 30, 2026, with a pre-bid site visit scheduled for September 30, 2026.

[View original listing](https://les.procureware.com/Bids/4666da10-5add-433e-b9e9-d80e20b5477c)