Meeting
7-21-2026 Cole County Commission Meeting
Body
ColeCountyMo
Date
July 20, 2026
Jurisdiction
State & Local
The Cole County Commission meeting on July 21, 2026, included a construction update on the new juvenile facility. The project was reported to be progressing on schedule, with steel and framing in place and interior trades beginning; roof and mechanical work were expected in the coming months. Commissioners discussed eventually selling the existing juvenile facility, but no sale date or bid process was set; September or October was mentioned as a possible time to plan next steps. No new construction contract award was recorded. The Commission also considered a $50,700 capital purchase from Knox Company for controlled-substance storage safes used by EMS, citing failures with the current safes and regulatory requirements. A motion to approve the purchase and related request form was made, though the transcript does not clearly capture the final vote.
The Commission approved a network-switch purchase, with 26 switches to replace aging equipment at county facilities, including EMS, Public Works, the health department, courthouse and sheriff’s office. The clearly stated motion was for $174,763.48, associated with Cisco and Huber and Associates; the purchase was said to save about $41,000, include three years of service, and support installation during the remainder of the year. The vote was recorded as unanimous among those voting. Commissioners discussed how IT capital costs are allocated among departments and funds, noting a need for clearer budgeting and advance notice in future budget cycles. Accounts payable was approved pending review; no other procurement decisions were clearly identified.
Source
ColeCountyMo