Meeting

Planning Commission - 9/14/26

Body

County of Sacramento

Date

September 13, 2026

Jurisdiction

State & Local

🏗️ Construction & Infrastructure Physical Infrastructure

The County of Sacramento Planning Commission held a meeting on September 14, 2026, primarily to consider a use permit amendment for the Aspen Six project, which involves a request for a four-year time extension to complete reclamation work on a 752-acre site where mining has already been completed. The commission reviewed the environmental exemption status and community planning advisory committee recommendations. A motion to approve the extension of reclamation activities until December 31, 2030, was unanimously passed and will be forwarded to the Board of Supervisors. No new mining or construction was proposed, and no public comments were made during the meeting. The commission also confirmed the next meeting date and had no additional scheduling or public comment items.

Source

County of Sacramento