City of Richmond Sanitary District Board of Commissioners of Tuesday, July 28, 2026
Body
WCTV Channels 11, 20 & 21
Date
July 27, 2026
Jurisdiction
State & Local
⚡
Energy & Utilities
🏗️
Construction & Infrastructure
Physical Infrastructure
The City of Richmond Sanitary District Board of Commissioners held a meeting on July 28, 2026, during which they approved previous meeting minutes and invoices totaling $42,587.21. Key procurement discussions included a recommendation to enter into an agreement with Power Plant Service Inc. for the repair of the sludge heater at the wastewater treatment plant, with an estimated cost of $30,000 on a time and materials basis. The board also approved a contract with Oler's Fence Inc. for $6,400 to connect existing fencing to newly installed entrance gates. Both motions were approved unanimously. No other procurement or budget items were discussed.
Source
WCTV Channels 11, 20 & 21