The City of Watertown Public Works Commission held a meeting on April 22, 2025, focusing on several procurement and infrastructure projects. The commission approved sidewalk repair orders for three locations and awarded a contract for the Plaza Phase 2 ADA concrete ramp improvements to Moss Brothers, selecting an alternative design option under budget. Additionally, the commission discussed and approved a significant multi-year project to replace lead water laterals throughout the city, with an estimated total cost of $7.8 million and a city cost share of approximately $1.25 million after grants. The funding strategy and budget implications for this project were key discussion points, emphasizing the importance of managing costs without impacting customer rates. Motions related to contract awards and funding allocations were passed by roll call votes.