Meeting
McCart McPherson Construction Meeting
Body
City of Fort Worth
Date
June 18, 2026
Jurisdiction
State & Local
The City of Fort Worth held a public meeting on June 18, 2026, to discuss the McCart McPherson Roadway Construction project. The project aims to improve safety and connectivity by expanding existing roadways and constructing new segments, including two-lane and four-lane divided roads, roundabouts, and three bridges over bodies of water. The construction is scheduled to begin in July 2026 and is expected to be substantially complete by July 2028, with funding primarily from the city's bond program and transportation impact fees. The meeting included a detailed overview of the project scope, phasing plans, and responses to community questions regarding traffic impacts, road connections, and project scheduling. Attendees were encouraged to use the city's My Fort Worth app and project webpage for ongoing updates and communication.
Source
City of Fort Worth