2026 06 02 Special Board Meeting

Body

Arlington_WA_School_District

Date

June 04, 2026

Jurisdiction

State & Local

📚 Education 🏗️ Construction & Infrastructure Physical Infrastructure

The Arlington WA School District held a special board meeting on June 2, 2026, primarily to discuss and approve a contract for the Arlington High School re-roof project. The district staff presented details about the competitive bidding process, with CDK submitting the lowest responsive bid of $2,228,000. The project will be completed in two phases, addressing roofing and gutter replacements to improve energy efficiency and resolve existing leaks. The funding for this $2.2 million project comes from the 2024 capital levy, with a total project budget of $4.7 million. The board unanimously approved the contract, authorizing the commencement of the re-roofing work scheduled through summer 2027.