The City of Lawrence Indiana Utility Service Board meeting on July 23, 2024, focused on approving key contracts and change orders related to utility infrastructure projects. The board approved a service agreement with KY Contracting LLC for an emergency sanitary force main repair and a $225,000 change order with Conexo Inc. for additional pothole hauling work as part of the EPA-mandated lead service line inventory project. Updates were provided on ongoing sewer cleaning and inspection efforts to support the 71st Street inflow and infiltration reduction project, as well as progress on the Fort Harrison sanitary sewer capacity improvements project. The meeting also addressed budget considerations related to the use of a $400,000 forgivable loan to ensure compliance with EPA requirements.